Bureaucracy
Responsibilities
Best Practices
100

What ACM section covers construction and unserviceable areas?

341

100

Will each construction project require the exact same marking, lighting and identifications?

No

100

When should we inspect the construction areas?

Every day before the crew leaves. After inclement weather. Before re-opening a surface. After a new phase starts.

200

What is the primary goal of ACM section 341?

Minimize disruption of normal operations

200

What are the two part 139 inspections that take place during a construction project. 

Continuous - during construction activities

Special - before re-opening an area

200

If you have any questions, where should you look for answers?

Ops department, CSPP in Ops Drive under construction projects and Lorin

300

What are the primary tools (documents) to ensure safety compliance when coordinating construction activities on the airport?

CSPP and SPCD

300

Name some items the airport operator (PTAA) is responsible for during a construction project?

Ensuring CSPP compliance (FOD, Stacking, etc.)

Issuing NOTAMs for changes

Inspection and ensuring part 139 compliance (protection of Navaids, etc.)


300

Name three commonly missed items at the beginning of a construction project or new phase.

Proper equipment placement (staging)

Confusing signs

Uncovered lights

Barricade placement and/ lighting

Construction signs not properly placed

400

Which AC sets forth guidelines for operational safety on airports during construction?

AC 150/5370-2G

400

The Safety Plan Compliance Document details what?

Timing and methodology on how the contractor will comply with the CSPP.

400

Construction has a lot of variables depending on the project. Can you find an issue?

Provide 100 pts for correct answer for a total of 400pts.