Site Entry+General
Rules and Training
Records and Plans
Permits and Prevention
100

 Contractors must check in with this department and obtain a temporary pass upon entering the Lindt site.

What is Security?

100

Contractors must provide and wear proper fall protection when working above this height.

What is 48 inches?

100

Contractors must notify the Company of the location and quantities of these materials

What are hazardous materials?

100

Contractors must follow these guidelines or "Practices" when entering the facility and performing job tasks.

What are GMPs

200

The maximum speed limit on the Lindt site is this many miles per hour.

What is 15 miles per hour?

200

When riding any vehicle on Lindt property, this safety device must be used.

What are seatbelts?

200

Contractors must submit this type of plan to the Lindt contact/project manager one week prior to any planned crane lifts.

What is a certified pick plan?

200

Special attention must be given to prevent an explosion when working in areas where this is present.

Combustible Dust

300

 This product is not allowed to be used anywhere on the Lindt campus.

What is tobacco?

300

Extension cords used in wet work areas must have this safety feature installed.

What is a GFCI (Ground Fault Circuit Interrupter)?

300

The company maintains a file on active contractors using this contractor and information management platform.

What is ISN | ISNetworld?

300

Contractors who work on live circuits must be trained in this safety standard.

What is Arc Flash safety/NFPA 70E?

400

Contractors must maintain documentation that each employee has received and understood training in these topics.

What are safety topics?

400

Contractors must use this type of equipment as a last resort to protect employees from hazards.

What is personal protective equipment (PPE)?

400

The company must be notified prior to any of these activities, regardless of how minor.

What are digging, trenching, or excavation activities?

400

Contractors must obtain this type of permit before commencing welding, cutting, or grinding (outside of Designated areas in the maintenance shop).


What is a Hot Work Permit?