General
Inputs
Tools
Outputs
100
Project Management Process Group where "Control communications" is contained.
Monitoring and Controlling Process Group.
100
The input of the Control Communications Process excludes all except

- Expert Judgment.
- Meetings.
- Issue Log.
- Change Request.
- Issue Log.
100
Requires discussion and dialogue with the project team to determine the most appropriate way to update and communicate project performance, and to respond to requests from stakeholders for information.

This definition corresponds to:

- Meetings
- Phone calls
- Skype chat
- Meetings
100
The output of the Control Communications Process includes all except

- Change Requests
- Work Performance Information
- Project Communications
- OPA Updates
Project Communications
200
Knowledge Area where "control communications" is contained.
Project Communications Management
200
Which of the following are Organizational Process Assets?

a) Specific communication technologies available.
b) Allowed communication media.
c) Record retention policies.
d) a and c.
e) all of them.
e) all of them.
200
Provides a set of standard tools for the project manager to capture, store, and distribute information to stakeholders about the project’s costs, schedule progress, and performance.

The description above correspond to:

- Information Management Systems.
- Organizational Process Assets.
- Meetings
Information Management Systems.
200
The following is a plan that gets updated as a result for control communications:

- Project Management Plan
- Communications Management Plan
- Progress report
- Project Management Plan
300
Which one is the definition of control communications?

- Develop an appropriate approach and plan for project communications.

- Process of monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met.

- Manage Communications (process of creating, collecting, distributing, storing, retrieving and the ultimate disposition of project information).
- Process of monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met.
300
What is Project Management Plan?
Plan describes how the project will be executed, monitored, controlled, and closed
300
Name at least 2 tools or techniques for Control communication.
Information Management Systems.

Expert Judgment.

Meetings.
300
Which of the following documents get updated as a result of control communications?

a) Forecasts.
b) Performance reports.
c) Issue log.
d) b and c.
e) all of them.
e) all of them.