100
The only appropriate area for "Restricted Area" signs to be posted in other languages (in addition to English).
What is overseas areas only?
100
DAC may delegat to senior intelligence officials of the Combatant Commands the authority to approve what?
What is Temporary Secure Working Areas (TSWAS), Temporary SCIFs (T-SCIFs), and concept statements for creations of new SCIFs.
100
These people conduct a one-time construction project review before site acquisition.
What is Service CSA or DoD Component SIO (or designee)?
100
This must not be used more than 40 hours a month, and no longer than 12 months in the same location.
What is a TSWA?
100
This person is designated by component SSO for each new construction or renovation project and they develop this.
What is a SSM and What is a CSP?
200
Main entry point combinations and any applicable bypass keys are stored here.
What is a different SCIF of same or higher accreditation?
200
a) physical security requiremens that cannot be met b) explanation of why the security requirement cannot be implemented, and he mitigations that were considered. c) mission impact if waiver is disapproved. d) ID of countermeasures tthat can be implemented to reduce residual risk. e) the time expectation on when the standard can be met and a waiver is no longer required.
What is information that must be included on a waiver?
200
This is the first critical element in the establishment of a SCIF.
What is Concept Approval?
200
This is used in support of tactical, contingency, and field training operations for a limited time.
What is a T-SCIF?
200
These are SSM's responsibilities.
What is 24 hour access, responsible for access control, verifying no uncleared workers during non-duty hours, establish security files (work schedules, picture id's, etc)
300
Facility's location and identity as a SCIF shall be protected at a minimum of this.
What is FOR OFFICIAL USE ONLY?
300
1 year, or until the waiver is no longer needed.
What is the time period a waiver can be granted for?
300
These are all of the steps required to establish a Scif.
What is 1. Concept approval 2. Commander sends request for SCI to service CSA's etc 3. Service CSA's etc validate need 4. Service CSA's provide concept approval (and DD 254 "contract sec. classification specs" if applicable)
300
Elements establishing or operationg a T-SCIF within a deployed theater will notify respective Combatant Command SSO within this time frame.
What is 48 hours?
300
This shall be submitted to the DAC at the 30% design point, along with completed risk assessment.
What is the CSP?
400
On releasable documents (bid requests, permit requests, sub-contractor plans), SCIFs should be referred to by this term.
What is Controlled Space or other terminology?
400
SCIF security begins with this.
What is the decision the build a SCIF.
400
The most stringent will be applied.
What is the standards that will be applied of OSPB standards and DoD standards conflict (unless resolved by DAC and Depat of State Bureau of Diplomatic Security)
400
These are the 4 types of Permanent SCIFs.
1. SWA- SCI not stored- any used must be stored in SCIF at COB or destroyed. 2. Continuous Operations- 24/7 3. Open Storage- SCI can be openly stored without using GSA approved storage containers 4. Closed Storage- all SCI must be stored in GSA approved container
400
THESE will be performed on construction personnel, and at a minimum be local record checks by mil., pass and id offices/local police/or local CI offices. If it reveals THIS, the individual will lose access. The SSM will maintain THIS
What are Security Checks? What is a felony or otherwise great risk? What is a list of authorized workers?
500
ICD 705 provides physical security requirements. If they can't be followed, this is required.
What is a waiver?
500
This is the first critical element in the establishment of a SCIF.
What is Concept Approval?
500
DoD SCIFs established within diplomatic facilities fall under security responsibility of this person, and they must also obtain this.
What is the COM and they must obtain permission through Dept of State channels to build a SCIF.
500
On a case by case basis and with justification, a DAC may approve this for a TSWA.
What is SCI storage for up to 6 months.
500
These are needed for access control of a construction site.
What is a unique project site picture id and temp. pass system? -must also include entry/exit screening and search procedures, prominent signs with prohibited items, and physical security barriers.