Calculations
Earned Value
Earned Value Too
Formulae
More Formulae
100

Your project has an EV of 600,000, SPI =1.23, CPI = 0.76. This value has been calculated to be 487,804.88.

What is the PV?

100

Tells what amount of money we plan to spend for the whole project.

 What is BAC or Budget at Completion?

100
It is what we expect the budget to be at the end of the project given the information we now have.

What is the Estimate At Completion?

100

EV - AC

What is CV?
100

BAC/CPI

What is EAC?

200

Your project has AC of $750,000 SPI = 0.68 CPI = 0.87. This value is calculated to be 959,558.82

What is the PV?

200

Tells us how far we are behind or ahead of schedule.

What is SV or Schedule Variance?

200

It is the cost we have to spend from this point to complete the project

What is the Estimate to Complete?

200

%Complete X Budget

What is Earned Value?

200
EAC - AC

What is ETC?

300

Your project has a CV of -81,000, SPI of 1.19 and PV = 560,000. It is calculated to be 747,400.

What is the AC?

300

Tells what value we are getting for every dollar spent

What is Cost Performance Index? (CPI)

300

The amount that we are over or under budget as of today?

What is VAC or Variance at Completion?

300

EV - PV

What is SV?

300

BAC - EAC

What is VAC?

400

Your project has an SPI of 0.92, a CPI of 0.75. You have spent 400,000. You are in the third month of a six month project. What is 652,173.91?

What is the Budget at Completion? (BAC)

400
Tells that we are progressing at specific percent of the rate we originally planned
What is SPI (Schedule Performance Index)?
400

Indicates that a critical path activity took longer than planned because work is being done at 89% of the rate we planned.

What is the SPI?

400

EV / AC

What is CPI?

500

The project has an SV of -47,000 and a CPI of 1.02. The PV is 130,000. The project is 12 months in duration and it is the beginning of Month 4.

It is calculated to be 460,000.

What is the ETC?

500

Tells us whether we are over or under budget.

What is Cost Variance or CV?

500
The value of -25,000 was the result of requiring more materials to finish the project.

What is The CV<?