Budget Updates
Subcontracts
Purchase Orders
Owner Contracts
Tax
100

What two items must you bring to your budget update?

Procore budget and supervision projection.

100

True/False: EBCO's subcontract requires subs to be responsible for their own daily cleanup.

True.

100

How much retainage is typically held for a purchase order?

0%

100
What does the acronym GMP stand for?

Guaranteed Maximum Price

100

Who pays sales tax for a vendor providing services to a project, but not registered in the state where work is performed?

EBCO

200

True/False: If you have a contingency log, it is not necessary to bring to a budget update unless changes have been made.

False. A contingency log should be brought to every budget update - no excuses. 

200

What is the traditional maximum contract amount for a short form contract?

$15,000* 

*dependent on the scope

200

How is freight shown on a Purchase Order?

Freight costs should be broken out as a separate line item or it should specifically be noted as included. Freight should be a firm number and not an estimated amount. Freight IS taxable.

200
What is the standard owner contract that EBCO uses on lump sum contracts? Are the terms always the same?

A101 and no they're different for various owners.

200

You're working on a commercial remodel project or new construction for a tax exempt entity, and go to buy a new power tool. Is this purchase taxable?

Yes. Sales tax is always paid on tools and incidentals that are not physically incorporated into the project.

300

If you're extending your schedule past your contractual time, even without an approved change order to extend time, you _________ extend your supervision projection

a) should

b) should not 

a) should

300

Is a subcontractor bound to an owner contract to the same extent that EBCO is bound to it?

Yes.

300

How is sales tax shown on a Purchase Order?

Sales tax should always be broken out as a separate line item and the percentage rate and amount should be verified.

300

Where do you find information regarding who should be carrying the builders risk policy?

The owner contract qualification/clarifications exhibit, and the AIA Exhibit A Insurance document.

300

Is the first finish out of a tenant space taxable as a new build or as a renovation?

A new build. Any future finish outs will be taxed as a remodel.

400

What is the key to a successful budget update?

A) Updated Procore budget

B) Updated contingency and allowance logs

C) Current owner & sub change orders

D) All of the above

D) All of the above

400
If you want to supplement a subcontractor on your job, what are the necessary steps?

First, issue a 3-day notice via email and certified mail. Contact the subcontractor. At the end of day 3, you must send a Supplement Letter. 

*Don't rely solely on email correspondence. Phone communication should be part of this process. 

400

True/False: When issuing a purchase order on a tax exempt job, it is not required to list a line item for tax on the PO Description table.

False. You should still have a line stating tax is not included and applicable resale certificate is attached.

400

Do you need to read an Owner Contract?

Yes.  As a PM you need to understand a number of critical terms in an Owner Contract, including schedule, delays, and payment terms.

400

During a new build project there is a water leak that causes a significant amount of damage but EBCO/subs are going to pay for out of pocket without involving insurance. Would remodel tax rules apply to the rebuild and why or why not?

No. Remodel tax rules would not apply because it is all part of a new construction project.

500

Where would you look to find information on the current billing cycle of a rented forklift in order to project accurately?

Job Cost History - last invoice will show the billing cycle

500

True/False: EBCO's subcontracts are net 30 payment terms. 

False. Payment terms are always paid when paid. *This is non-negotiable.

*Exceptions to be run through Michele

500

What does a Purchase Order provide to EBCO that a simple credit card purchase does not provide?

Insurance protection to EBCO if the materials are lost or damaged in transit.

500

What are the budget implications of a cost savings split in a GMP contract?

A portion of URG and other unspent funds will be returned to the Owner at completion of the project and this should be accounted for in budget updates.

500
You're working on a remodel and issue an owner change order. Do you break out sales tax as a separate line item on the change order?

Yes. Always break out remodel sales tax on each owner change order.