3-501-01
3-520-01
3-530-01
3-540-01
3-550-1
100

Secondary side of service entrance transformer

What is the location of the NEC demark?

100

15%

What amount of spare capacity is required in the electrical system?

100

LED lights

What are we to use for interior lighting?

100

• In a separate room of the same building that houses the generator

system.

• In a building separate from the building served by the generator system.

• On the outside of the building that houses the generator system.

• On the outside of an enclosure that contains the generator system.

Where does an emergency power off switch need to be?

100

Bond both ends of the conductors to ground

What do we do for the 4th wire (neutral) on primary systems?

200

It's a "why" document.

What is the basis of design?


200

1200amps and larger

At what rating is switchboard construction needed?

200

4100 CCT

What is the minimum color temperature for interior lighting?

200

7 days

What is the required fuel tank size?

200

24" burial depth

What is the minimum depth to underground condutis?

300

Connected load x a demand factor

How do you size a service entrance transformer?

300

hinged panel fronts

What's another name for door-in-door construction?What does the UFC require, but specs don't say?

300

80 CRI

What is the minimum color rendering index?

300

4 pole

What kind of transfer switch is usually required?

300

conduit stup out

What do you provide from the HV section of a service transformer? 

400

3% for feeders, 3% for branch circuits

What are the allowed %'s for voltage drop?

400

1/2" conduit size

What is the minimum allowed conduit size?

400

all lights turn on

What should happen when the fire alarm goes off?

400

isolation bypass

What kind of ATS do you need for critical facilities?

400

1/3 spare

How many spare conduits do we need in ductbanks?

500

Calculated load values

What must our panel schedules show?

500

20amp circuit breaker

What's the minimum branch circuit overcurrent protection?

500

+/-10%

What is the allowed deviation of indicated lighting levels/criteria?

500

because it's a critical system

Why do we have to witness acceptance testing?

500

T and Y splice

What's not allowed in manholes for greater than 15kv sytems?