500
The comprehensive, necessary, and mandated review of all inspection requirements is based on all eight (8) of these fundamental documents. The inspector will review this applicable dynamic set of documents to fully comprehend the scope and breadth of work for the project that will be performed.
What are project drawings, specifications, contractor schedule, approved submittals, RFI Responses, new bulletins, weather conditions, and emails?