Schedule Performance Metrics
Cost Performance Metrics
Implementation of Earned Value Management
100

When the value of work performed is less than the value of work scheduled

What is a negative Schedule Variance (SV)

100

When BCWP is less than ACWP you have this

What is a negative Cost Variance (CV)

100

He brought the concept of EVM to the Department of Defense from the automotive industry

Who is Robert McNamara

200

When the value of work performed (BCWP) is equal to the Budget at Complete (BAC) it means this

What is a completed project

200

Actuals plus this value determines the Estimate at Complete (EAC)

What is the Estimate to Complete (ETC)

200

This DoD document provides a clear and uniform interpretation of the 32 EVM Guidelines

What is the Earned Value Management System Interpretation Guide (EVMSIG)

300

A project is experiencing this if it has reached the end date of its Baseline Budget, yet its BCWP is less than its Budget at Complete (BAC)

What is a schedule overrun or schedule slip - may also be called an Over Target Schedule (OTS)

300

A project is experiencing this if its cumulative actuals exceed its Budget at Complete (BAC)

What is an Over Target Baseline (OTB) or cost overrun

300

This company document describes how project teams will implementation the 32 EVM Guidelines

What is the Earned Value Management System Description (EVM SD)