BAC
Budget at Completion
CPI
Cost Performance Index
VAC
Variance to Completion
Actual % of work (x) BAC
EV (Earned Value)
Earned Value (EV) / Planned Value (PV) =
Schedule Performance Index (SPI)
PV
Planned Value
SV
Schedule Variance
TCPI
To Complete Performance Index
Budget minus New Forecasted Budget =
VAC (Variance at Completion)
Budget at Completion / Cost Performance Index =
Estimate at Cost (EAC)
EV
Earned Value
SPI
Schedule Performance Index
SPI
Schedule Performance Index
Earned Value (EV) - Actual Cost (AC) =
CV (Cost Variance)
Estimate at Cost (EAC) - Actual Cost (AC) =
Estimate to Completion (ETC)
AC
Actual Cost
EAC
Estimation at Completion
CPI
Cost Performance Index
Earned Value (EV) / Actual Cost (AC) =
CPI (Cost Performance Index)
Budget at Completion - Estimate at Completion =
Variance at Completion (VAC)
CV
Cost Variance
ETC
Estimation to Completion
BAC
Budget at Completion
Earned Value (EV) - Planned Value (PV) =
SV (Schedule Variance)
(BAC - EV) / (BAC - AC) =
To Complete Performance Index (TCPI)