Earned Value Basics
Organization
Misc
100

The acronym represents the originally planned $ amount of work to be performed from finish to end of the project

What is Budget at Complete (BAC)?

100

This contract document outlines the work the customer wants to be done

What is a Statement of Work (SOW)?

100

We never do this in Earned Value Management to evaluate a project's current performance.

Compare Budget vs Actuals

200

The acronym represents the remaining dollar amount of work to be performed to complete the project

What is Estimate to Complete (ETC)?

200

This identifies the organizational entities responsible for managing and executing the work.

What is an Organizational Breakdown Structure (OBS)

200

This is something we use to identify how a work package is able to earn performance.

What is an Earned Value Technique (EVT)?

300

This acronym represents the originally planned dollar amount of work to be performed up to the current status date

What is Budgeted Cost of Work Scheduled (BCWS)?

300

This is a product based hierarchical decomposition of a project’s scope into smaller, manageable components

What is a Work Breakdown Structure (WBS)?

300

This is an Earned Value Technique we use to identify tasks that are far out in the future and have not been planned out with much detail yet.

What is a Planning Package (PP)?

400

This acronym represents the amount of actual money that has been spent so far to do work in the Project

What is Actual Cost of Work Performed (ACWP)?

400

This is a word we use for the smallest unit we use to breakdown work within a Project's scope.

What is a Work Package?

400

Major Program Events, Significant Accomplishments, and Accomplishment Criteria are all part of this document 

What is an Integrated Master Plan (IMP)?

500

This acronym represents the dollar amount of the original baseline plan that we have earned thus far up to the status date

What is Budgeted Cost of Work Performed (BCWP)?

500

This is a term we use for a rollup of Work Packages that is used as a management control point in a project where scope, budget, actual costs, and schedule are integrated and measured for performance.

What is a Control Account?

500
This is created at the intersection of a WBS element and an OBS element

What is a Control Account?