What is a type of Risk Identification that you can easily see what will make you late?
Technical performance is compromised
Technical risks are too great
Project now lacks strategic fit
Customer's needs have changed
Competition threatens project results
A new, superior alternative has emerged
What type of termination reviews all on-going activities for completion and closure?
2. Revisit the Need
3. Manage Resource Impacts
4. Te the Loose Ends
5. Capture the Experience
What type of termination tells you that a lot can be learned from a termination?
isolate significant variances and identify the reasons they occurred, emphasize the quantitative and specific rather than the subjective and general, and describe specific corrective actions taken and planned
Information that has no real value except as it is used effectively in the management of the project. It does not automatically lead to an effective management process. Info does not ensure success, but lack of info can contribute to project failure.
What type of termination accounts for all resources used, available and requiring disposal?