It's My Money and I Need it Now
Shipping & Handling
Order in the Court
Phased & Confused
Misc.
100

T/F When you order products, designer's "cost" is the same as designer's "net".

True

100

Vendors might accept an order cancellation but may charge a _____ fee.

Restocking

100

What does PO stand for?

Purchase Order

100

Which phase are acknowledgements received in?

5. Contract Administration

100

What does FOB stand for?

Free on Board

200

What is the difference between a Flat Fee and an Hourly Fee?

Flat Fee - a fixed agreed upon amount

Hourly Fee - paid for the amount of hours worked

200

____ ____ ____ means ownership of merchandise while items are on the common carrier.

(Hint: usually said as an acronym)

FOB Free on Board

200

Should the client see your POs?

No

200

Which two phases of the design process can a change order ocur in?

4. Contract Documents

5. Contract Administration

200

What does CPM stand for?

Critical Path Method

300

What does "Net 30 Days" mean?

30 calendar days from receiving the invoice to pay

300

Is the designer or the vendor responsible for the items in transit when terms are "FOB Factory"?

Designer

300

Choosing another pricepoint of option is defined as ____ engineering.

Value

300

Define "deliverables".

Documents to be shared with clients/users.

300

During the Scope of Services Analysis, always ask if there is a _____ file that exists. This is known as the "as-built drawing."

AutoCAD

400

What is a disadvantage of the Flat/Fixed fee method?

Heavily dependent on the accuracy of the budget

400

Is the designer or the vendor responsible for the items in transit when terms are "Freight Prepaid"?

Designer

400

Name or model # is what kind of specification?

A. Reference

B. Proprietary

C. Performance

D. Descriptive

B. Proprietary

400

Put these Phase 5 tasks in order of when they should ideally be done. (there are other tasks that may be done in between these as well)

Install Lighting

Frame Walls

Install Furniture

1. Frame Walls

2. Install Lighting

3. Install Furniture

400

_____ ______ is all of the money that comes into your business.

Gross Revenue

500

DPE means direct ____ expense and it is the what the company has to pay in order to have a ____ on staff.

Personnel

Designer

500

A potential problem is if the client doesn't realize the freight is FOB Factory or Freight Prepraid, but the client does not have insurance to cover ______ during truck transportation.

Damage

500

Notations reliant on industry standards is what kind of specification?

A. Reference

B. Proprietary

C. Performance

D. Descriptive

A. Reference

500

Place these tasks in order of when they happen during a Phase 5 kitchen install:

Install electrical wires in framed wall

Install drywall

Install flooring

1. Install electrical wires in framed wall

2. Install drywall

3. Install flooring

500

In interior design, what does "dye lot" mean?

The material was died together at the same time.