General Trench Reporting For Duty
The simple slope requirement for a general excavation in type "C" soil, 20' or less in depth is?
What is 1 1/2:1 - 1 1/2ft horizontal for every 1 ft vertical
This company must be called at least 3 days prior to any digging to let them know you could be working near underground utility lines?
What is Miss Utility?
Three things you should potntially test for before entering a trench with contaminated soils, and periodically while working within a trench are?
What are oxygen, flammability and toxic gases
The simple bench requirements for a trench must be in this soil
What is type "B" soil