Processes
EVM
Business Rhythm
SAP
Cobra
100

This document defines how F-35 implements PPMP requirements and describes our different processes in relation to program performance management. 

PPMD

100

This metric measures cost efficiency 

(BCWP / ACWP)

CPI

100

This meeting occurs in Week 2 where CAMs must justify changes +/- $100K to their control account.

ECR Board

100

This process can move material actuals from one charge number to another in SAP.

Journal Entry

100

This button must be pressed each month in order to determine BCWP

Calculate Progress

200

Time phasing changes outside the Freeze Period for all elements of cost (excluding discrete scope and COS) follow this baseline change process

eWAD WCR

200

This acronym represents work contractually authorized but not yet negotiated

AUW

200

Baseline changes must be approved in EWAD by this day.

Sunday (Acct. Month End)

200

This transaction code can show you what material you have on order (i.e. net open commitments)

CJI5

200

This button allows your cost class to update to the latest rate file that has been selected

Recalc

300

This process occurs every 12 months and requires bottoms up analysis, documented rationale, and approvals of forms.

CEAC

300

This acronym is budget withheld by the PM for any unknows / risk management.

MR

300

The IPMR Submittal (Formats 1-5) is due on this day.

17th Business Day (Week 4 - Day 2)

300

This transaction code is where you set up new CLINs, work packages, etc.

CJ20N (Project Builder)

300

Actuals on a WP in SAP that is not set up yet in Cobra will land here

Unassigned Actuals

400

EAC Reasonableness is justified by CAMS when it trips certain thresholds in this monthly document.

EVAR

400

This acronym represents the contract time-phased budget plan

PMB

400

This excel document is sent out on Day 1 of the Business Rhythm to all CAMs, PMs, and Finance team.

BATS Log

400

This tool can be used to pull large SAP requests in a shorter amount of time and will send you the report once its done running

RABBIT

400

This report provides a quick snapshot or extract of the data within your project, including code fields and EV techniques (don't forget to update totals first!)

All CAWP

500

This is the person you send your JE to for processing

FP&A Lead

500

This metric is calculated by:

ACWPCUM + [BCWR ÷ (0.8 CPICUM + 0.2 SPICUM)]

weighted IEAC

500

The BCR Board approvals are done by these 3 people.

Program Manager, Finance Manager, & Planning Manager

500

This costing sheet must be selected on each level of the project to ensure PMO burdens are correctly applied.

ZCBKB1

500

This specific resource file must be selected when setting up Ancillary Files on a new project

M_F35PMO