Which of the Governmentwide Acquisition Contracts is considered a Best-in-Class source for IT acquisitions and has a website with a duck endlessly swimming in circles?

NASA SEWP V

100

$250,000.00 (significance of this amount to us in contracting)

Simplified Acquisition Threshold (SAT)

100

FAR 13.004: When a contractor submits a quote in response to an RFQ, is this a binding agreement?

A quotation is not an offer and, consequently, cannot be accepted by the Government to form a binding contract.

The order is an offer by the Government to the supplier to buy certain supplies and a contract is established when the supplier accepts the offer.  

100
***Daily Double*** Agreements made by Government personnel lacking contractual authority are called an ___________ ; However, the Government may, at its discretion adopt an unauthorized act as if it were authorized and this is called _____________.
unauthorized commitment and a ratification
100

What cost means the total cost to the Government of acquiring, operating, supporting, and (if applicable) disposing of the items being acquired.

Life-cycle cost

200
Which option may be exercised more than once, but may not exceed six months total? And what is the  number of the associated FAR clause?

The Option to Extend Services, FAR 52.217-8.

200

Who must review review complaints from a Contractor concerning all task-order and delivery-order actions for a contract and ensure the Contractor is afforded a fair opportunity for consideration in the award of orders, consistent with the procedures in the contract?

The Ombudsman

200

FAR 13: When a CO shall solicit quotations orally to maximum extent practicable (under what circumstances)

Under SAT, oral solicitation if more efficient and notice is not required [FAR 13.106 (c)(1)]

200

What is the key difference between multiple year and multi-year contracts?

IAW AR 17.103, multi-year contracts buy more than one year’s requirement (of a product or service) without establishing and having to exercise an option for each program year after the first. F

200

What legal rule states that certain clauses are of such importance in public procurements so as to be considered incorporated by operation of law?


Christian Doctrine

300

**DAILY DOUBLE** ______ is the guidance on format for structuring Government solicitations and contracts when using Contracting by Negotiation (in other words, a table of contents for organizing contractual documents into four parts and 13 sections).

Uniform Contract Format (UCF) (FAR 15.204-1)

300

**Daily Double** Where do you find information about cost and price negotiation policies and procedures in the FAR? 

FAR 15.4...which prescribes the cost and price negotiation policies and procedures.

300

Which type of analysis shall be used when certified cost or pricing data are not required?

Price analysis (FAR 15.404-1)

300
Has limited delegated authority, appointed (in writing) by the CO to assist in the technical monitoring of service contracts.
Contracting Officers Representative (CORs).
300

What document must be approved to justify restricting consideration to an item peculiar to one manufacturer?

Brand Name Justification

400

What process is appropriate when it may be in the best interest of the Government to consider award to other than the lowest priced offeror or other than the highest technically rated offeror?

Tradeoff Process (FAR 15.101-1)

400

In what phase of the acquisition process must market research occur?

ALL of them.

400

What FAR subpart states that simplified acquisition procedures may be authorized for commercial products or commercial services for acquisitions that do not exceed $15 million?

FAR 13.5

400

Which act prohibits federal agencies from obligating or expending federal funds in advance or in excess of an appropriation, and from accepting voluntary services?

Anti-Deficiency Act

400

How many required sources of supply are called out in FAR 8.002?


Five

500

The special form of written approval by an authorized official that is required by statute or regulation as a prerequisite to taking certain contract actions?

Determination and Findings (D&F)

500

Which action excludes a contractor from Government contracting and Government-approved subcontracting for a reasonable, specified period?

Debarment

500

What FAR provision pertains to Offeror Representations and Certifications - Commercial Items

FAR 52.212-3

500

What type of service describes an action that cannot be divided into two or more parts without negatively effecting performance of the task?

Non-severable

500

What type of contract places the maximum risk and full responsibility for all costs and resulting profit/loss to the contractor?

Firm Fixed Price Contracts