This is the type of Work Order is used to install Firmware.
Field Service Bulletin.
What is NET45
Payment term requiring a client to pay an invoice in full within 45 calendar days of the invoice date
I need this as a minimum to work in the field.
CPR/AED/First Aid
This "free text" can be found on both the Site Report and the Work Order
Detailed accounting of the work performed.
I can find information on expense items and the expense policy here.
US Services Travel, Expense & Allowance Guidelines - FSR home page
I do this for incorrect WO's on site.
Contact the planner to correct the WO and confirm the correction.
The point the customers are sent the invoice
WO is set to complete
This is the SE Policy number for LOTO
SE460
I can do a repair and PM on the same report
When I have a PM and Repair WO and attach the report to both WOs.
This is the maximum time allowable to submit an expense report before it is late.
<30-days from the moment the expense was incurred.
This is the term for the amount of time the SRs are scheduled for a job
Planned Duration
The term used for the LoB to cover costs
Technical Risk
This is the system to log a Safety Opportunity or Safety Incident.
EcoOnline
I do this on a job that is not yet completed.
Call TS/Planner to order parts and create FU WO.
This is needed when requesting an Admin WO
The reason for the WO & TM permission
At what point is reporting a deviation in the WO mandatory?
Stages 7 & 8
The P&L stage my actions impact a job's revenue
This is the GVX LIMITED APPROACH boundary
30M (10Ft.)
The Tuner/Log files I add to the WO
Pre & Post work Tuner/Log files
This is the proper time to submit a Vehicle Maintenance TER
After it is done in order to account for actual time. - **Do not check all day box**
This is when a WO is complete
When that activity SOW is complete within the scope.
Customer is only charged for the parts when...
We "Consume" those parts in the WO or flag them as left on site as spares.
An approach limit at a distance from an exposed energized electrical conductor or circuit part within which it is considered the same as making contact with the conductor or circuit part
Prohibited Approach Boundary
What is the proper naming convention for a site report?
OnSite_TechRpt_WO-07983596_210409-100612
...Is required at the completion of the work
Send the report to the customer and close the WO.