Safety
Food Safety
Inbound
Outbound
Sortation
100

The maximum stack height allowed when team lifting CHEP pallets

What is 8 pallets?

100

The correct temperature ranges for Chilled and Frozen products in SSD Grocery

What is Chilled: 33–41°F / Frozen: at or below 0°F 

100

The temp check SLA after completing the TDR process

What is 3 minutes?

100

The order that carts should be processed to ensure fairness and SLA compliance

What is First In, First Out (FIFO)?

100

The correct order you should prioritize your carts for stow based on chill chain

What is Frozen → Chilled → Ambient?

200

The EPJ AA operating near your area must do this BEFORE you can safely proceed through the zone

What is make eye contact with you and sound the horn?

200

The protein type that belongs at the BOTTOM following the Raw Meat Stow Hierarchy

What is whole and ground poultry?

200

The temperature reading that would require an escalation for a Chilled shipment that just arrived

What is above 41°F ?

200

The critical rule that must be followed when manually assigning picklists in STORM's Search and Resolve tab

What is never assign a mix of temperature zones (e.g., chilled and frozen) to the same associate?

200

The correct process of handling driver returns, even when the package is still intact and cold

What is NEVER re-induct — process through RTS/RTFC regardless of condition?

300

PPE that is required for associates working alone in the freezer environment

What is Lone worker device, cold weather gloves, freezer jumpsuit, face covering, and boots ?

300

The frequency and deadline the Food Safety Audit (iAuditor) must be completed by

What is weekly, by end of day on Saturday?

300

The latest a 6AM produce shipment can be stowed by

What is 12PM (6 hour SLA)?

300

When a picker exhausts all inventory locations and shorts an item, it moves to...

What is moves to 'Problem Solve' status in HWMS — a problem solver completes a guided pick flow to validate the short?

300

The meaning of a route still showing as "Stow Pending" with a stage by time 25 min away and the leadership action that should be taken

What is Grocery packages have NOT been stowed yet — escalate immediately to ensure stow completion before the window closes?

400

The incident type that requires ONE OR MORE days away from work, excluding the injury date

What is Lost Time Incident?

400

The time frame a site has to submit a Corrective Action Plan after a failed Steritech audit

What is 5 days?

400

The two views in the Marauders Map Incoming Shipments Tab and what they show

Scheduled Tab and Calendar View - both used for IB forecasting and planning your flow

400

The purpose of the daily bag audit procedures in Gravion, and which personnel are authorized to execute them

What is 10 ambient + 10 chilled bags per site per day (split 5 AM shift / 5 PM shift per zone), performed by L3+, focusing on quality, packaging, and accuracy?

400

The meaning of "Picklist Assignable Dwell >20 min" and the correct leadership action

What is A picklist was ready and assignable in STORM but nobody picked it up for more than 20 minutes — the fix is active STORM monitoring and immediate manual assignment before the window closes?

500

The amount of people REQUIRED to lower or raise a bulkhead plus the additional member that must also be present

What is 2 AAs minimum plus an L4+ leader?

500

The TWO conditions that will AUTO-FAIL on a Steritech audit and immediately end with a score of zero

What is swollen/bloated cans on shelf and live rodents or roaches on produce?

500

The site target % for Stow Without Manifest (SWM)?

What is less than 1%?

500

Known Item Shorted definition and the difference between a True Pick Skip and a False Pick Skip

What is KIS measures orders/units containing shorted items; True Pick Skip = item was truly missing; False Pick Skip = picker marks an item missing but it was actually available?

500

The three main failures that are UTR Controllable that lead to a high Late Stage Discrete%

What is Late/No Pick, Late/No Stow, and Late/No Batch — site-controllable UTR execution failures where each step's lateness cascades to everything downstream?