Period of Performance
IDIQ
Firm Fixed Price
100

Y/N: Can we pay our supplier invoice even though it came after the POP End date? 

YES

100

What does ICITAP and OPDAT stand for?

International Criminal Investigative Training Assistance Program (ICITAP) and Office of Overseas Prosecutorial Development, Assistance and Training (OPDAT)

100

Who assumes the most risk?

Amentum (Contractor)

200
Situation: TO Execution date was 10/1/24. POP is 10/12/24- 12/31/24. What date can we start accruing cost?

10/12/24

200

What OY is 08/01/2023- 07/31/2024

Option Period III

200

Can negotiate your competitive subcontractors after source selection?

YES

300

When should the RA notify GSCM to Close open PO's?

When the POP Ends
300

T/F: Sole sourcing is discouraged, as it limits the ability to ensure fair and reasonable market pricing for items.

TRUE

300

T/F: Training courses are not allowed to be FFP per the contract

FALSE

400

When do you put in a request for a no-cost Modification to extend the period of performance?

When costs are going to be incurred and billed after POP End date.

400

The purchase of premium class tickets may be considered, if what is submitted?

Medical Certification

400

In order to get a higher fee, what do you need to communicate to the contracts/proposal team?

RISK

500

When do you put in a request for a no-cost Modification to "pull to the left" the period of performance?

When costs are going to be incurred prior to the original start date.

500

What is the ceiling value of this contract?

$750,000,000

500

What is the SINGLE biggest risk we currently have on our FFP TO's

Transportation (Customs, Shipping)