Agile
Knowledge Areas & Process Groups
Math
Processes
Tools & Techniques
100

This is the term for a timebox for a product increment.

What is a Sprint?

100

This knowledge area is the only one that has at least one process per process group and is considered the main role of a Project Manager.

What is Integration Management?

100

The value of work completed so far.

What is Earned Value?

100

The Collect Requirements process is part of this knowledge area.

What is Scope Management?

100

This is the term for the tool/technique where lower level cost estimates for work packages in a WBS are summed for a given cost account.

What is cost aggregation?

200

This is the term for the list of requirements or user stories for a Sprint.

What is the product backlog?

200

These three knowledge areas do not include any processes for the Executing process group.

What are Scope Management, Schedule Management, and Cost Management?

200

The formula for this earned value metric is BAC - EAC

What is VAC (Variance at Completion)?

200

The processes of Perform Integrated Change Control and Validate Scope are part of this process group. 

What is Monitoring and Controlling?

200

This tool/technique uses an algorithm to estimate cost or time using historical information and project parameters.

What is parametric estimating?

300

These include the product backlog, the sprint backlog, and the increment.

What are sprint artifacts?

300

These three knowledge areas only have 3 processes; one each for the process groups of Planning, Executing, and Monitoring & Controlling.

What are Quality Management, Communications Management, and Procurement Management?

300

This is the formula for calculating the Pert or Beta Estimate

What is O+4M+P/6?

300

This process is the only one of the Initiating process group that is not part of Integration Management.

What is Identify Stakeholders?
300

These are the strategies for overall project risk.

What are avoid, exploit, transfer, mitigate, and accept?
400

These people/teams make up the Scrum team

Who are the Product Owner, the Development Team, and the Scrum Master?

400

This knowledge area has 4 processes; one each for the process groups of Initiating, Planning, Executing, and Monitoring & Controlling.

What is Stakeholder Management?

400

This formula is for the earned value metric To Complete Performance Index (TCPI)

What is (BAC - EV) / (BAC - AC)?

400

The Estimate Activity Resources process is part of the Resource Management knowledge area, but these two activity-related processes are included in the Schedule Management knowledge area.

What are Define Activities and Estimate Activity Durations?

400

This tool/technique is a predetermined list of risk categories that might give rise to individual project risks or may act as sources of overall project risks.

What are prompt lists?

500

These are the 4 values of Agile.

What are Individuals and interactions, Working software, Customer collaboration, and Response to change?

500

These are the knowledge areas.

What are Integration Management, Scope Management, Schedule Management, Cost Management, Quality Management, Risk management, Communications Management, Resource Management, Procurement Management, and Stakeholder Management?

500

This is the formula for calculating Future Value (FV)

What is PV x (1+i)n?

500

The four estimating techniques of Analogous, Parametric, Three Point, and Bottom Up Estimating are used for these two processes.

What are Estimate Activity Durations and Estimate Costs?

500

Performance Reviews, Risk Probability & Impact Assessment, and Cost of Quality all fall into this category of tools & techniques.

What is Data Analysis?