ECR´s
ECR´s and ECO´s
ECR´s
ECR
ECR´s
100

What is the Meaning of ECR?

Engineering Change Request

100

What is the status of the ECO when the ECR is in Plan ECO?

a) Produced

b) Released

c) In work

b) Released

100

Complete the sentence

Once your doccuments are connected to the ECR, inform the ________  ______ of your request

Project Team

100

Complete the sentence

ECR approver and _______ give their agreement by signing the ECR

QUALITY

100

If the change is manage by Technical Group... who is the ECR approver?


Technical group Manager

200

What is the Meaning of ECO?

Engineering Change Order

200

What is the status of the ECO when the ECR is in Complete?

a) Produced

b) Released

c) In work

a) Produced

200

Who can cancel the ECR?... at the stage of Evaluate

a) the requester

b) the pilot

c) the manager


b) the pilot

200

Who can create an ECR?

a) Product Line Manager

b) Any user

c) The buyer for Supplier changes

b) Any user

200

Who can promote from Review to Plan ECO

a) PM, PQE

b) PLM, TGM

c) Any user


b) PLM, TGM

300

The ECR IS Manadory before Tooling KO

True

False

False... it is not mandatory

300

Where should be storage a change impacting raw material?


GRP STANDARDS RAW MATERIAL...

300

Complete the sentence

Once the impact analysis completed, the Pilot promotes the ECR at state of _______

Review

300

Who can promote to submit the ECR?

a) Product Line Manager

b) Any user

c) The buyer for Supplier changes

b) Any user

300

How many signatures are needed to Complete the ECR?

a) 1

b) 0

c) 2

c) 2

400

The ECR Is not mandatory post Tool KO

True

False

False...the usage of ECR is mandatory

400

When do we need to add the Change request document in the ECR at PDM?...what status

a) Submit

b) Create

c) Initial

b) Create

400

Who promotes the ECR to Plan ECO?

a) The Pilot

b) The Engineering Manager

c) the ECR Approver


c) the ECR Approver

400

Who can promote from submit to evaluate?

a) PM, PLM, TGM

b) PLM, TGM

c) PQE, PM, PLM

a) PM, PLM, TGM

400

At what stages the ECR could be cancelled?

a) create, submit, evaluate

b) submit, review, plan Eco

c) evaluate

b) submit, review, plan Eco

500

What is part of the Impact Analysis - Evaluate status of ECR?

a) Parts impacted, drawing or 3d impacted by modification

b) Appointment of Pilot, Initialization of tracking sheet

c) Confirmation of Kick off, action plan and review

a) Parts impacted, drawing or 3d impacted by modification

500

In PDM can we update and modify the inputs of ECR once created?...Expecting complete answer why or when...

Yes

No

Yes, until plan ECO

500

Who connects the ECR with the ECO?

a)The designer

b) The Pilot

c) The ECR approver

a)The designer

500

Complete the sentence

If an ECO is connected to the ECR, it has to be promoted at __________ before by the __________ ___________

Produced

Project Manager

500

What are the current indicators on CLI02 related to ECR´s?

% ECR open more than 1 year <= 20%

% ECR with start in production in delay <= 5%