The project review is a brief meeting to confirm the ______ __ _____ _______in the progress meeting to decide on the project's status based on the risks. It is planned according to the schedule and done on time
status of each task
Within the project team, the ____ represents the Customer.
PQE
What happen with the PR status if a major task is NOK?
project review refused
When_...after RP6,
In a project... PM must escalate the information to PLM or engineering manager to follow it in QRQC level 2 with the managers concerned
1 month
What task is this one
Output:
* List of production sites selected + associated volumes
• List of tools and resources used by plant selected
• List of standard blocks to use during the project.
• List of skills transfer need to be driven to different plants
Master plan
Complete
During project reviews, involving at the minimum ____ ______ of the tasks which need to be reviewed
the pilots
Who ensures the consistency of completion with the help of “example sheets"?
The PQE
Complete
All the gaps of the project reviews, identified must be recorded in ____ ______ ______
with the decision (action, deadline and pilot)
the action plan
When and how a project could be closed by Hierarchy agreement?
In this case, only
deviations without M (major) remain (confirmed by quality records of the mass
production) and /or Costs targets have not been completely achieve.
6 months after RP6, the members of the CPP must submit the information of the
tasks not closed, the reason why they’re not closed and the remaining risk to the
Product Line Director and Regional EVPO to ask for their agreement for project
closure.
What is this task... Inputs
Technical and Economic folder and Matrix Compliance
(List of Exceptions during Customer Quotation)
• AKWEL questions (Template Questionnaire by Product
Family)
• Customer requirement
Interactive Questionaire
Who is is responsible for the planning, organization and animation of all Project Reviews?
The Project Manager
A real status that meets the expected state at the time of the Project Review Project will be _________ ___ in the column « Current Status »
reported OK
the actions from others meeting (CPP, customer…), reviews such trial run, the preproduction and manufacturing process audit could be
....Where?
followed in the unique action plan
During the SOP, the gap analysis between the PRC and PRP is performed. In case
of discrepancy, the cost component is rated at 5 and the risk of “___________”
a) Cost
b) Management
c) Quality
b) management
Who is the pilot of Prototype Validation?
Laboratory and/or CMM and test
Each evolution of the project review is noted in the
____________ comment until it is validated.
versioning
A real status which does not meet the expected level at the time of Project review will be ______ ____ in the column « Current Status
reported NOK
True or False
The action plan of the previous project review is a "major" task
True
Definition
Term used to describe recycled materials, natural fibers and bio-materials used in the automotive industry to increase the proportion of recyclable
parts
Green Material
What is this task...
Inputs: Customer specifications, standards
• Functional analysis
• DFMEA
• Product validation blocks (FVP)
• Drawings
Pilot: DE
Validation Plan definition
Complete
The pilot will confirm that ________ ____ ________ expectations (with the help of ________ ______) are done and documents are available as defined in
the Work Instruction
AKWEL and customer
example sheets
Who... Need to evaluate the associated risks for each gap with the help of example sheet and the tab criteria of the component?
PM with PQE and the pilot
If a PR is refused ...what needs to happen?
Explain
n the event of a REFUSED project review and risk below than 30, the product line
manager is informed to follow the Major gaps in QRQC Product Line department
(level 2) to accept the review as soon as possible by reducing the risk.
Only the Product line manager (after exchange with the PGM if necessary) can
accept on the base of the action plan to continue the project at “Refused” status.
If the risk is higher is 30 or more, the Product Line Manager must escalate it to
Product line director to follow the action plan until it 30 or more and inform all
managers concerned and the customer if necessary. ( Escalation principle : see
CLI02-01-005)
What task is this one... Output
List of tasks and pilots
Quality Plan
What is this task...
Inputs
* Suppliers panel
• Detailed offers from suppliers and supplier suggested
• CDC signed by the suppliers
• Industrial equipment Standards
Tooling sourcing committee