This initiates each phase of the new load interconnection process.
What is an application?
This is the software platform where all action items and large load projects are tracked.
What is Monday.com?
SPP studies do not start until this phase.
What is Phase II?
The official launch date of implementation for Sunflower's Load Interconnection Process.
What is August 18?
This is the name of the group email address that should be included on all email correspondence for load interconnections involving Sunflower.
What is loadaddition@sunflower.net ?
The preliminary rate analysis is delivered in this phase.
What is Phase I?
This form is housed in Monday.com and is used as the mechanism to collect data from potential projects.
What is the Phase Applications?
This purely informational, non-binding request is submitted by Sunflower to SPP.
What is the informational AQ?
A project requires a fee schedule starting at this megawatt level.
What is 25 MW and above?
The initial screening analysis is performed by this SME.
Who is Ryan Yokley?
Called project development, this phase lasts four months to two years.
What is Phase III?
This is how I can expect to be notified I have been assigned a task to support this process.
What is An auto-generated email from Monday.com.?
SPP states that they will turn around all studies within this timeframe.
What is 90 days?
After each project phase, Sunflower will issue this for any outstanding study deposits.
What is An invoice?
The point of contact for all SPP studies is this SME.
Who is Nathan Pearce?
A one-line diagram and preliminary cost estimate are packaged together in this Phase II study.
What is the preliminary facility design study?
Every large load project in Monday.com will have this item to track progress between phases.
What is the Checklist?
If a transmission upgrade is needed to serve a specific load, but isn’t classified as a network upgrade through SPP, the cost responsibility falls entirely on this party.
What is The applicant?
To ensure timely service, this is required for all fees and deposits before any work begins in each project phase.
What is Payment in advance?
This SME ensures capacity for resource adequacy requirements when a sleeved PPA is not involved.
Who is Erica Schmidt or Corey Linville?
The introduction of the Member and Sunflower to the end-use consumer indicates you are ready to transition into this phase.
What is Phase III?
This is the dashboard that rolls up all the project information, phases, and location data, serving as the resource for project updates.
What is the Prospective Load Dashboard?
This is a pre-requisite to file the AQ through SPP.
What is a RESA?
This is the main difference between a study deposit and an application fee.
What is Refundable vs Non-refundable?
This is the mechanism that outlines the rates, standard terms and conditions for service between Member, Sunflower and load applicant.
What is The RESA?