Transformation
Transmission
Underground
Switching
Rubber Gloving
100

What type of a core is most commonly used in a distribution transformer?

Shell Type

100

When determining conductor weight, the safety factor for spans 250 ft or greater is.

1.5

100

When making hand contact with underground primary conductor :

An equipotential zone must be created

100

How many cycles will an electronic recloser take to trip open when the Hot Line tag is in  the on position:

4-6 cycles

100

What is the maximum voltage the class 0 gloves are rated for?

1000 V

200

What causes ferroresonance?

No secondary load on transformer bank during switching.

Three phase transformer installation with a primary connection other than grounded wye.

Energizing by means of single pole switches.

200

Two important pieces of information that must be attached to every live line tool test decal are:

Date, Test facility

200

When remotely grounding a cable for work:

Positive cable identification must take place after grounding the cable

200

What is the rating of a solid blade in a cutout:

300A

200

The test interval for rubber gloves is:

6 months

300

A transformer that is manufactured to alter customer voltage in 5% intervals has what installed?

Tap changer

300

The Design Factor for rigging components used to support personnel is:

10:1.

300

What must you do after a grounding elbow has been used, before it can be used again?

 Inspect for damage, clean and lube.

300

Operating Order 2T-27 governs Distribution feeder switching using disconnect switches.

TRUE

300

Before opening a conductor, what percentage of the load must the bypass jumper be carrying?

30%

400

The secondary windings of a 120/240V transformer are put in series and the transformer is 96% efficient, what is the secondary voltage?

120 / 240 V

400

As per WorkSafe BC, OSH Regulation Part 34, the only rope construction that is approved for rescue purposes is:

Static Kernmantel

400

How do a cable fault indicator operate:

A magnetic field produced by a fault passes through the fault indicator enabling it to operate

400

What should be done to a voltage regulator before parallel switching (same source) outside the substation?

Set to NCO

400

When completing a rubber glove job, in general how is coverup removed?

First on, last off

500

One transformer on a delta-delta bank is burned out and the bank is hooked up open delta-open delta. What is the capacity of the 2 remaining transformers?

86.6% of remaining 2

500

The intent of the equipotential zone is to establish a low ________ path, parallel to the workers.

Impedance

500

A PLT is testing a cable using a Hastings Phase Tel with Hi Pot adapter. The meter indicates line to ground voltage and maintains that reading. What does this indicate?

The cable has a bolted fault

500

What two ratings are shown on an S&C Load Buster tool?

600A nominal/ 900A maximum

500


What is the grace period on rubber protective equipment?

No grace period