Safety
Quality
Line 1 Glidepath
Line 5 Glidepath
Line 12/Other
100

What percent BOS completion did we end October with?

100%%%%%

100

How many QSFs did Line 1 have in October?

ZERO!!!!
100

What is Line 1 Unplanned Stops Goal for December?

60

100

What is Line 5 Unplanned Stops Goal for December?

40

100

What is Line 12 PR Goal for December?

83%

200

How many near misses do we track per month per line?

4! One per team for every line

200

How many QSFs did Line 5 have in October?

2

200

What is Line 1 PR Goal for December?

58%

200

What is Line 5 PR Goal for December?

63%

200

What EO is coming to Line 12 in December?

ZzzQuil

300

How many safety improvements should be completed per month for each team?

1 per team for every line

300

How many QSFs did Line 12 have in October?

ZERO!!!

300

What is Line 1 Unplanned Downtime Goal for November?

22%

300

What is Line 5 Unplanned Downtime Goal for December?

20%

300

Which line had the best MU for October?

Line 5

400

What is our monthly safety focus?

Pallet safety and pinch points

400

What is our target QSFs for November?

ZERO!

400

What is Line 1 Planned Downtime Goal for November?

20%

400

What is Line 5 Planned Downtime Goal for December?

17%

400

What is the CBN Unplanned stops target for the plant at the end of the fiscal year?

24 Unplanned stops

500

When was our last safety incident?

April 2013

500
What does GMP stand for?

Good Manufacturing Practices

500

What is/was Line 1 MSU Target for November?

857

500

What is/was Line 5 MSU Target for November?

158

500

What are the three parts of being a P&G technician?

Equipment owner, Area owner, and System owner