DEFINITIONS
APPLIED KNOWLEDGE
ENERGY
LOTO DEVICES
6 STEP PROCESS
100

Another name for Lock Out/Tag Out? 

What is Energy isolating?

100

Reading the procedure is a good way to start.

What is the first step in beginning a LOTO?

100

Electrical ___ is the most common form of energy to be locked out.

What is energy?

100

Name this LOTO device:

What is Hasp

100

This step includes notifying all affected employees in the area that the equipment is going to be shut down and locked out.


What is Step 1 Prepare for Shut Down

200

The first person to apply a LOTO device is considered to be this

Who is a LOTO owner?

200

DAILY DOUBLE: 400 points

During this phase, store or residual energy MUST be relieved to make it non-hazardous.

What is Stored Energy Check or Stage 5?

200

Electrical capacitors and air/water/gum lines.

What are ways to store energy?

200

Names this LOTO device:

 

What is Plug lock?

200

Step 2  is Shut Down of the Equipment.

Involve the _______ who normally shuts down the equipment.


What is the affected employee/worker


300

Something that tells you how to properly perform LOTO?

What is a LOCK OUT/TAG OUT Procedure?

300

Done when there is no other way to remove a lock, you must try to contact the authorized employee before performing this procedure.

What is cutting off the lock?

300

This may mean any number of things like turning off the electricity at the breaker.

What is isolating the energy?

300

name this LOTO device:

What is Fuse cover?

300

This step includes:  Remember to stand to one side when opening electrical disconnects in the event of electrical arc occurs.

What is Step 3 Isolate the Equipment?

400

Energy that is stored but could be released.

What is potential energy?

400

When employees fail to recognize when/where/why/how to apply LOTO devices.

What is LOTO training? 

400

___________

-Produced as a result of a chemical reaction

___________

-Water vapor kept under pressure so as to supply energy for heating or mechanical work

What are Chemical & Steam

400

Name these LOTO devices:

 

What are Circuit Breaker cover & Wall Switch cover

400

Step 4 is titled _____________.


What is APPLY LOCK OUT/TAG OUT DEVICES



500

DAILY DOUBLE: 1000 points

Must be used whenever you are performing service or maintenance on any machine where you or someone else could be injured by the unexpected startup or release of stored energy

What is LOTO?

500


At this point, an authorized employee verifies the device has been isolated and de-energized.

What is the Isolation verification?

500

The isolation of hazardous energy. It is an important part of any safety program. 

LOTO or Lock Out Tag Out or Energy Isolation?

500

Name this LOTO device:

 

What is LOTO lockbox?

500

In Step 6, the technician must_______________ using testing equipment like voltmeters, thermometers, manometers, etc....


What is Verify isolation or Zero Energy?