Environmental Stewardship
NPDES
NPDES Part 2 of 2
Vegetation
Non-Compliance/Independent QA
100

The National Pollutant Discharge Elimination system was developed as part of this Act

NPDES permit regulates discharge of pollutants form point sources to waters of the US

What is Clean Water Act

100
This size LOD triggers NPDES permit

What is 1 acre

100

Notice once the project is completed, stabilized, and the ESC controls removed with MDE approval

what is Notice of Termination


Note Standard Inspection form must be completed until Notice of Termination is received and approved by MDE

100

Topsoil purchased for use on SHA Projects

what is furnished topsoil
100

Regional Environmental Coordinator (REC) QA rating grades that are considered in compliance

What is a grade of A, B, or C


(FYI grades of D & F shut down work and require re-inspection within 72 hours)

200

How often is yellow card recertification required

What is every 3 years

200
Length of public notice period for NOI

What is 14 day public notice period

200

Event that discharges a significant amount of sediment

What is Triggering Event

Requires identification and inspection with documentation, notify MDE within specified time frame, determine corrective action

200

Requirement for fertilizer applied to State lands

what is nutrient management plan

200

Number of hours a contractor has to make corrections after a C rating

what is 72 hours

300

This document has the highest governing order of the contract documents

What is Special Provisions in the IFB.

Governing Order Highest to Lowest: Special Provisions in the IFB, Plans, Special Provision Inserts, Standard Specifications

300

Maximum amount of pollutant that a body of water can receive while still meeting water quality standards

What is Total Maximum Daily Load (TMDL)

300

Period of time NDPES standard inspection forms must be archived from the date of permanent stabilization

What is 3 years

300

Temporary mulch is applicable when area will be disturbed again in ____ months

& temporary seed is applicable when area will be disturbed again in ____ months

What is 2 months for temporary mulch & 2-12 months for temporary seed

300
Contractor payment to SHA for each day the project has a D or F rating
what is liquidated damages
400

This certification is the prerequisite for MDOT SHA certification

What is MDE Responsible Personnel Certification (REC)

400

Measurement of particles suspended in water

What is Nephelometric Turbidity Units

(MDE currently uses visual observations for turbidity instead of lab testing)
400

Interval Standard Inspection form must be completed

What is weekly (Sunday through Saturday) and after every rain event resulting in runoff

400

Lifespan of Type A SSM

what is 12-24 months

400

Form REC fills out to grade Contractor ESC

What is OOC 61/QA-1 Inspection Checklist

500

ESC Document that must be on site at all times

What is 2011 Maryland Standards and Specifications for Soil Erosion and Sediment Control

500

MDE notification required when an exceptional incident where there is an unintentional and temporary noncompliance due to failure of technology or unforeseen events

What is 'Notice of Upset'

Upset notice of proof is on the permittee (ex. filter bag failure while contractor is following manufacturer recommendations)

500

Section of Clean Water Act that specifically required EPA to develop and implement NPDES program

What is Section 402

500

Location where Type D SSM is applicable

what is natural areas 

(ex. wetlands)

500

Penalty for falsifying records upon conviction

What is imprisonment for up to 2 years and/or $10,000 fine