Documentation
Workflow
Compliance
Pitfalls
Wilshire Process
100

This 3-part form is the standard industry document used to apply for payment.

What is the AIA Pay Application (G702/G703)?

100

This is the typical time window (in days) for a lender to review and approve a draw.

What is 5–7 days?

100

This federal act requires specific "prevailing wage" reporting for many projects.

What is the Davis-Bacon Act?

100

This action occurs when a PM bills for more work than has actually been completed in the field.

What is Over-billing?

100

This term describes the percentage of the contract sum that is withheld until final completion to ensure quality.

What is Retainage?

200

This document, when signed, proves that a subcontractor has been paid for their work and waives their right to place a lien on the property.

What is a Lien Waiver?

200

This step is triggered the moment a draw package is submitted to the lender.

What is ordering the Draw Inspection?

200

This should specifically NOT be included in the subcontract price in both Arizona and Mississippi (two states with active Wilshire projects).

What is Sales Tax?

200

A draw is "frozen" if this type of document for a subcontractor is expired.

What is an Insurance Certificate?

200

This is the document needed to legally change the contract price or scope.

What is a change order?

300

This is the detailed budget breakdown that acts as the roadmap for the entire project's expenses.

What is the Schedule of Values (SOV)?

300

This is the key site visit that must occur before the lender releases funds.

What is an Onsite Inspection - Draw Walk?

300

This requires recipients of HUD funding to direct employment, training, and contracting opportunities to low-income individuals and the businesses that employ these persons within their community. 

What is Section 3?

300

This is the result of submitting a draw package without owner sign-off.

What is a Rejection/Delay?

400

This report verifies field progress matches the requested funds.

What is an Inspection Report?

400

This is the usual frequency of the construction draw process.

What is Monthly?

400

This financial reserve is kept to cover unexpected costs without delaying the draw.

What is a Contingency?

400

This happens when a change order is billed before it is legally executed.

What is a Billing Discrepancy/Audit Flag?

500

These five items typically make up a standard "Draw Package."

What are Invoices, Waivers, SOV, Change Orders, and Photos?

500

If a draw is submitted late or missing documentation, this is the most likely consequence for the construction schedule.

What is a delay in funding (and project slowdown)?

500

This type of documentation is required to ensure that local or minority-owned businesses are being used, a common requirement in affordable housing funding.

What is MWBE (Minority and Women-Owned Business Enterprise) reporting?

500

This occurs when the actual costs of work exceed the budget line item for that task.

What is a Cost Overrun?

500

These types of funds are usually exhausted first before a loan starts its draw.

What is Project Equity?