HOLD MY BEER
(Safety)
OOPS, WE HAVE TO DO IT AGAIN
(Quality)
LONDON BRIDGE IS FALLING DOWN
(TSCD)
EVERYONE'S WORKING THIS WEEKEND
(Schedule/Planning)
IT'S NONE OF YOUR BUSINESS
(Financial Reporting)
100

These 10 keys to success for Front-Line Supervisors can help them be safety leaders.

What is the FLS Top 10?

100

This person is the Underground District Quality Manager.

Who is Glen Tonack?

100

More commonly known by the acronym TSCD

What is Temporary Structures and Construction Devices?

100

The planning process we follow has this many steps

What is 6?

100

More commonly known by the acronym LPR

What is the Labor Productivity Report?

200

This manual houses all of the Underground specific safety policies.

What is the District Safety Reference Manual?

200

A plan which outlines the requirements for inspection and testing.

What is an Inspection and Test Plan (ITP)?

200

The person responsible for Initial Project TSCD Matrix sign off

Who is the Underground District Manager?

200

This schedule is reviewed at the start of each shift

What is the Plan of the Day (POD)?

200

Crew hours and quantities should be completed at this time.

When is the end of shift?

300

These two programs make up the proactive reporting structure for the district.

What are LSA Assessments and Observations?

300

More commonly known by the acronym ASTM

What is American Society for Testing and Materials?

300

The 3 risk levels for temporary designs

What are low, moderate, and high?

300

This is the first step of our planning process

What is Plan the Plan?

300

The project cost details report should be reviewed this often

What is Weekly?

400

Every operation must have these two documents in place, current, and signed before starting work.

What is a Build Plan and Start Card?

400

A point in an operation which must be verified by an independent authority or person before work can proceed.

What is a Hold Point?

400

This is required prior to a TSCD item's first use

What is an Initial Inspection and Documentation?

400

The staffing on a project is tracked on this schedule.

What is the Indirect Schedule?

400

Financial reporting is completed this often

What is Monthly?

500

These three programs make up "The Way We Do Safety" section of the Key Elements of Safety.

What are Craft Voice in Safety (CVIS), Life Saving Actions, and recognition programs?

500

This is meeting held with the Client to review the contractors Build Plan, Safety Plan, ITPs, Equipment, etc.

What is a pre-activity meeting?

500

According to the Underground Risk Matrix a pressurized utility system over 50 psi and under 200 psi is this risk category

What is Moderate?

500

A P6 schedule is made with this software

What is Primavera?

500

Production goals should be communicated this often

What is Daily?