The Job Is Talking to You
Foreman Said What?
Cost Reports
Math Time
PG University Reruns
100

A PM enters only half of the installed footage completed by the field crew. What will the report most likely show?

  • A. Higher profit
  • B. Better productivity
  • C. Lower project performance
  • D. Lower material pricing

 

C. Lower project performance

100

The foreman reports the crew installed 3,500 LF this week, but the PM has not updated quantities in two weeks. What should the PM do first?

  • A. Submit billing
  • B. Update quantity tracking
  • C. Close the project
  • D. Reduce manpower

B. Update quantity tracking

100

Installed quantities are accurate, but subcontractor invoices are missing. What will likely be understated?

  • A. Revenue
  • B. Material quantities
  • C. Schedule progress
  • D. Actual costs

D. Actual costs

100

The report shows:

  • Budgeted Cost at Completion = $1,200,000
  • Forecasted Cost at Completion = $1,410,000

What is the projected cost overrun?

  • A. $110,000
  • B. -$190,000
  • C. $210,000
  • D. -$310,000

C. $210,000

100

What was the topic of PG University Session 5?

Safety

200

Labor costs increased this week, but installed quantities stayed the same. What is this usually a sign of?

  • A. Great forecasting
  • B. Poor productivity
  • C. Higher material pricing
  • D. Faster installation

B. Poor productivity

200

The crew was budgeted to install 800 LF per week but completed 1,050 LF while keeping labor costs flat. What type of variance is this?

  • A. Negative variance
  • B. Neutral variance
  • C. Positive variance
  • D. Hidden variance

C. Positive variance

200

Costs are increasing faster than installed production (Crew should cost $80/LF but costs $92/LF). What should the PM be concerned about?

  • A. Shrinking margins
  • B. Extra manpower
  • C. Slower closeout
  • D. Lower billing

A. Shrinking margins

200

The labor budget is $15 per LF installed. The crew installs 900 LF with actual labor costs of $18,900. What was the actual labor cost per LF?

  • A. $15/LF
  • B. $18/LF
  • C. $21/LF
  • D. $24/LF

C. $21/LF

200

What was the topic of PG University Session 10?

811s and Communication

300

A crew completed additional work Friday afternoon, but the PM forgot to update quantities before Monday. What happens to the report?

  • A. Nothing changes
  • B. Costs disappear
  • C. Profit increases
  • D. Earned revenue may appear too low

D. Earned revenue may appear too low

300

A PM notices project costs trending higher than expected midway through the job. What advantage does the report provide?

  • A. Early corrective action
  • B. Automatic profit recovery
  • C. Reduced labor costs
  • D. Faster inspections

A. Early corrective action

300

The project budget expected 10,000 SF installed by this point, but only 7,500 SF is complete while 85% of labor dollars have already been spent. What should concern the PM most?

  • A. Weather reports
  • B. Shrinking profit margins
  • C. Vendor lead times
  • D. Office overhead

B. Shrinking profit margins

300

The report shows:

  • Actual Costs to Date = $640,000
  • Forecasted Cost to Complete = $410,000

What is the Expected Cost at Completion?

  • A. $950,000
  • B. $1,010,000
  • C. $1,050,000
  • D. $1,150,000

C. $1,050,000

300

What was the topic of PG University Session 6?

Subcontracts and Major POs
400

A PM needs to adjust future unit costs because material pricing increased unexpectedly. How should they accomplish this?

  • A. Adjust Quantity Tracking
  • B. Adjust Cost to Complete
  • C. Adjust PM Override
  • D. Adjust Revenue Recovery

C. Adjust PM Override

400

A superintendent warns that rain delays may reduce weekly production from 1,000 LF to 600 LF for the next month. Which section of the report should likely be updated?

  • A. Installed Quantities
  • B. PM Override
  • C. Payroll Setup
  • D. Equipment List

B. PM Override

400

The project budget estimated total costs at $1.8 million, but the PM Forecast Tool now predicts $2.05 million at completion. What does this indicate?

  • A. Forecasted cost overrun
  • B. Worsened profitability
  • C. Lower labor burden
  • D. A & B

D. A & B

400

The report shows:

  • Original Forecast = $2.4M
  • Updated Forecast = $2.7M
  • Project Revenue = $3.0M

What is the updated projected profit?

  • A. $200,000
  • B. $300,000
  • C. $500,000
  • D. $600,000

B. $300,000

400

What was the topic of PG University Session 8?

Bluebeam Workshop

500

A project’s projected profit keeps shrinking week after week. What should the PM investigate first?

  • A. Office snacks
  • B. Production rates and job costs
  • C. Contract schedule 
  • D. Truck mileage

B. Production rates and job costs

500

Installing more work than planned while maintaining stable costs usually improves what?

  • A. Profit
  • B. Fuel usage
  • C. Safety outcomes
  • D. Change orders

A. Profit

500

A project started with a planned gross profit margin of 18%, but the report now forecasts 9%. What does this tell the PM?

  • A. The project is outperforming
  • B. Financial performance is declining
  • C. Quantities are too high
  • D. A & B

B. Financial performance is declining

500

A MH Install item has:

  • A budget of $200,000
  • Quantity of 10 EA manholes
  • 0 MHs installed to date
  • $100,000 already showing in actual costs

The PM knows the $100,000 is for all the material that has already been purchased and delivered, not installation labor.

The PM Forecast Tool is currently showing a projected -$100,000 loss on the item.

What unit cost should the PM enter into the PM Override to correctly forecast the item?

  • A. $50,000
  • B. $100,000
  • C. $10,000
  • D. -$100,000

C. $10,000

500

What was the topic of PG University Session 2?

Project Startup