PSA
Resource Requests
Starting A Project
Running A Project
Closing A Project
100

What are the 3 main things that need to match in PSA?

Details on the main page

Milestone amounts

Actual/Projected hours

100

Ture or false - if you know who you want staffed, you put their name in the suggested resource field  

false

100

What is the first thing you should do when you get assigned to a new project?

make sure you understand what the scope is: check wbs, sow, pitch deck, and set up a meeting with the CS/BD/Scoping sme to understand the sold in project

100

What is variance?

Variance is the difference in the teams time submitted to forecast

100

What fields need to be complete to be able to close a project and what stage?

Project recap section and moved to completed

200

What fields on the details page need to be filled in?

Start date

End date

Bill rate

Planned hours

Contingency where necessary

Project manager

bill type

project type

200

True or false - every resource request needs to be associated with a milestone

true

200

What are the key things to get set up prior to kick off?

slack channel

share folder

time tracker

task tracker

esr

kick off deck

200

Why is variance important to manage?

for the team: helps to accurately forecast their schedule to inform practice leads on their availability 

for the company: helps to accurately forecast revenue 

200

What is a retrospective

A retrospective is a meeting with the internal team to review results, learnings, and opportunities for next time.

300

If a project just kicked off but the resources arent seeing the project show up for them in their timesheets, where would you look to solve the problem?

Check start and end dates in the details page

Check the start and end dates in the milestones

Check the project planner for hours in the current week

Check with CS that the opportunity is in verbal

300

What fields should be filled out in a resource request?

Milestones

suggested resource

start date

end date

requested hours

skills/certifications

300

What things are important to share with the team to ensure they are set up for success?

WBS

SOW

Pitch Deck

Kick off Deck

300

What document should you send to the clients on a regular basis?

ESR

300

Where should contingency be set on a project?

could be spread out throughout a project if CS/PL are aligned to impact monthly revenue


could be one month past to give leeway to moving end dates

could be the same month as closed project if we know for sure we are ending and CS is aligned

400

What happens if a project is "in progress" but the opportunity hasnt closed yet....and then the opportunity closes?  bonus: How do you avoid the issue?

The start dates on the details, milestones, and project planner bump out 2 weeks from the close date

you can avoid this by having the project in 'missing paperwork'

400

what resource request automatically gets requested when a project is made and why?

A PL so someone can have hours to set up a project
400

What things might you ask the client before even getting started to ensure you are set up for success?

Access

400

What should every meeting have and be followed up with?

Every meeting should have an agenda and be followed up with notes

400

When should you be communicating with the client about the end of the project?

At least a month before the end date you should be communicating with the client on aligning to expectations for what/when wrap up looks like

500

How are the 3 types of project types milestones set up?

time and materials - set up automatically with one milestone for the service type

fixed fee - set up by CS based on agreed payment terms

retainer - set up automatically with a milestone for each month

500

What happens if a resource request doesnt have a milestone against it?

The hours submitted wont show up as chargable

500

When should you aim to set people's times for the week ahead and approve time?

Set forecast the Friday before - a snapshot is taken EOD Friday to impact variance

approve time mondays - so the company can see revenue 

500

How do you know how much time the team needs week over week to manage variance?

Ask the team

Check trends after approvals on Monday


500

What additional conversations and when should you be talking to the client about to drive future work?

Wrap up presentation should be held up to a month before the end date