This Earned Value technique assigns 0% performance until a task is fully completed, at which point it jumps to 100%.
What is a 0/100?
These are the first inputs CAMs should provide to assist in developing the IMS
What are task names and durations?
These are major things that should be reviewed before a schedule risk assessment is performed or the IMS is baselined (name one).
The entire scope of work has been captured,
Schedule logic is complete and accurate,
Resources have been appropriately assigned,
Time-Phasing of Work is achievable
This technique assigns 50% performance when the task starts, but cannot gain any more until a task is fully completed, at which point it jumps to 100%.
What is a 50/50?
This convention is considered a best practice to develop a name for a task
What is a Verb + Adjective + Noun?
Activities that consume resources that are further out in the future and planned with less detail are called this.
What are Planning Packages
This Earned Value technique must be supported by a list of steps, or Quantifiable Backup Data, in order to evaluate how performance can be earned
What is a "% Complete"?
This is a statistical model that evaluates the likelihood of a project meeting key deadlines by analyzing uncertainties and risks within the schedule.
What is a Schedule Risk Assessment (SRA)?
This is a list of “increments” or subtasks within a tasks scope that are assigned performance values
What is quantifiable backup data (QBD)?