This Earned Value technique assigns 0% performance until a task is fully completed, at which point it jumps to 100%.

What is a 0/100?

100

These are the first inputs CAMs should provide to assist in developing the IMS

What are task names and durations?

100

These are major things that should be reviewed before a schedule risk assessment is performed or the IMS is baselined (name one).

The entire scope of work has been captured,

Schedule logic is complete and accurate,

Resources have been appropriately assigned,

Time-Phasing of Work is achievable

200

This technique assigns 50% performance when the task starts, but cannot gain any more until a task is fully completed, at which point it jumps to 100%.

What is a 50/50?

200

This convention is considered a best practice to develop a name for a task

What is a Verb + Adjective + Noun?

200

Activities that consume resources that are further out in the future and planned with less detail are called this.

What are Planning Packages

300

This Earned Value technique must be supported by a list of steps, or Quantifiable Backup Data, in order to evaluate how performance can be earned

What is a "% Complete"?

300

This is a statistical model that evaluates the likelihood of a project meeting key deadlines by analyzing uncertainties and risks within the schedule.

What is a Schedule Risk Assessment (SRA)?

300

This is a list of “increments” or subtasks within a tasks scope that are assigned performance values

What is quantifiable backup data (QBD)?