This activity type is a rollup of tasks. It can be expanded and collapsed.
What is a Summary Task
This is often better to use to represent a wait time instead of a lag
What is a Schedule Visibility Task (SVT)?
This is a the difference between a critical path and driving path
The critical path is the path that drives the very end of the project. A driving path is the path that drives any activity before the end of the project.
This activity type is a marker that represents a significant accomplishment and has no duration, work, or cost assigned to it.
What is a Milestone?
This is "The Law of Dependencies"
The predecessor MUST _____ before the successor CAN _______
What is a best practice for names of resources in Microsoft Project?
Resource names should be generic (ie. Systems Engineer, not Bob or John)
These are the three dependency types we can use between Predecessors and Successors in Microsoft Project
What is Finish-to-Start (FS), Start-to-Start (SS), and Finish-to-Finish (FF)
This is the best way to develop a name for a task
What is a Verb + Adjective + Noun
These are considered "Soft Constraints"
Start-No-Earlier Than (SNET), Finish-No-Earlier-Than (FNET)