As project manager, you are about to start the define scope process. You have the project charter, what other input do you need?

Requirements Documentation

100

What should be done by the project manager to make sure that all work in the project is included?

Create a scope statement

100

Completion of a product scope is measured against

WBS and WBS Dictionary

100

What is a tool and technique used in controlling scope of a project?

Variance Analysis

100

What is a template?

A form to help sort out all of the information for the project and have it organized to be used.

200

You’ve been put in-charge of a project. Which document should you read to identify the project constraints and the acceptance criteria?

Scope statement

200

You’ve just completed the Collect Requirements process. Which Scope Management process would you implement next?

Define Scope

200

During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project. Which of the following documents contains the detailed description of work packages?

WBS Dictionary

200

What tool or technique would a project manager use to control scope?

Variance analysis

200

Project schedule network diagram is an important output of which of the following processes?

Sequence activities

300

What is a valid input to the collect requirements process?

Project Charter

300

What is product acceptance criteria?

A way to define the process and criteria for accepting completed products, services, or result

300

Decomposition is an important tool used to

Create a WBS

300

What is Scope Baseline?

a summary description of the project's original content and end product, including basic budget and timeline data

300

What is an activity list?

A list that states all of the schedule activities needed for the project and a SOW description for each activity so the group knows what work is needed to complete the project

400
What is a project scope statement document?

A document that states was work needs to be completed during the project and what deliverables need to be produced by the project.

400

What is a product deliverable?

Deliverables include both the outputs that comprise the product or service of the project, as well as ancillary results, such as project management reports and documentation. The deliverables may be describes at a summary level or in great detail

400

What is the lowest level of WBS components known as?

Work Package
400

You are a new project manager that is replacing a previous project manager. You want to know more about the scope baseline of the project. Which three documents will be most useful to you?

Project Scope Statement, WBS, WBS Dictionary

400

Jasmine is very excited as she will be having her own apartment soon. She is just waiting for the day when she will get possession of her new home. However, she cannot start interior work unless the builder hands over keys of home after completion of electricity work. What kind of logical relationship can be said between these two activities?

Finish to Start

500

During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by the stakeholders’. The BEST thing for the project manager to do is t

Let the stakeholder know that the scope cannot be added

500

In your project, you want to ensure that each requirement adds business value by linking it to the business and project objectives. This also provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. The document that helps to achieve this is called..

Requirements Traceability Matrix

500

The Work Breakdown Structure can BEST be thought of as an effective aid for __________ communications.

Stakeholder
500

What is the order of the Scope Management processes?

Collect Requirements, Define Scope, Create WBS, and Verify Scope.

500

What is the term for an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level?

Rolling Wave Planning