Conflict Management
Project Documents
Stakeholders
Project Phases
Project Approach
100

Two teams working through a project conflict seek a win/win solution. Which conflict strategy should they employ? 

Compromise/Reconcile

Force/Direct

Collaborate/Problem-solve

Smooth/Accommodate

Collaborate/Problem-Solve

100

A construction company wants to follow proper processes for projects and their documentation. Which document serves as the official authorization for a project? 

Statement of work

WBS

Project charter

Project scope

Project Charter

100

A project manager has been told by another stakeholder that a project budget must be watched closely as a project progresses. Which stakeholder is most interested in making sure a project stays on budget? 

Team member

Project sponsor

Project manager

Manager

Project Sponsor

100

In which phase of the project life cycle are business needs determined?

Monitoring and Controlling

Executing

Planning

Initiating

Initiating

100

A hybrid approach combines elements of which project approaches? (Choose two)

Adaptive

Agile

Predictive

Waterfall

Adaptive 

Predictive

200

Match each conflict resolution type with its win/loss outcome. 

Compromise/reconcile 

Collaborate/problem-solve

Smooth/accommodate

Win/loss-win/loss

Win-win

Loss-win

Compromise/reconcile - Win/loss-win/loss

Collaborate/problem-solve - Win-win

Smooth/accommodate - Loss-win

200

Which part of a project management plan uses a Gantt Chart as a management tool?

Schedule

Risk

Scope

Budget

Schedule

200

Which stakeholder has the ultimate signoff decision on a project and its deliverables? 

Project sponsor

Project manager

Team member

Customer

Project Sponsor

200

Which parts of a project plan are interdependent during the planning phase? (Choose three)

Quality

Schedule

Scope

Budget

Acceptance

Schedule

Scope 

Budget

200

Which aspects are indicative of a predictive approach to project management? (Choose two)

Overall risk is assessed.

A critical path is established from start to finish.

Tasks are done in sprints to reach short-term goals.

Client demands change frequently.

Overall risk is assessed

A critical path is established from start to finish

300

A project team member raises an issue about quality defects in an app that is due to be released. The team member is insistent the issue be resolved so as not to embarrass the company developing the app. In response, the project manager insists that the app be released as is. What type of conflict management has been used?

Smooth/accommodate

Withdraw/avoid

Force/direct

Compromise/reconcile

Force/Direct

300

The definition of a project's objectives is found in which project management document?

Project charter

Business case

Procurement document

Project scope

Project Charter

300

A consulting firm is building an app for a company that sells various types of containers. In this project scenario, which stakeholder has the final say on whether the app was built to its required specifications?

Project Manager

Customer

Manager

Project Sponsor

Customer

300

In which phase of a project plan is a project charter created and approved?

Initiating

Monitoring and Controlling

Executing

Planning

Initiating

300

Which characteristics are common to the adaptive approach of project management? (Choose two)

A set list of deliverables

Scope creep

Rapidly changing requirements

A product backlog

Rapidly changing requirements

A product backlog

400

A team member approaches a project manager with an insistence on completing tasks in a different way than prescribed in the project plan. Even though the manager knows that the project plan contains the fastest way to complete these tasks, he acquiesces with the team member. Which conflict management strategy has been employed?

Compromise/reconcile

Smooth/accommodate

Force/direct

Withdraw/avoid

Smooth/accommodate

400

Which project document secures the services of and defines compensation for external resources?

Project Scope

MOU

Request for Bid

Contract

Contract

400

Which groups of stakeholders are responsible for functional testing for products created in a project plan? (Choose two)

Customers

Managers

Team members

Project Managers

Customers 

Team Members

400

In which aspect of the project life cycle does the process of verifying deliverables take place?

Executing

Closing

Initiating

Planning

Closing

400

Due to an increase in supply costs, a project manager indicates that a project is currently 5% over budget. What should the project manager do first to solve the budget problem?

Access money from the management reserve, if it is available.

Cut future supplies by 5%.

Access money from the contingency reserve, if it is available.

Cut the project scope by 5%.

Access the money from the contingency reserve, if it is available.

500

Two businesses are having conflicts over an interface design for an app. Eventually, the businesses meet and agree to implement some aspects, while each yields on others. Which conflict management strategy is being used?

Smooth/accommodate

Force/direct

Collaborate/problem-solve

Compromise/reconcile

Compromise/reconcile

500

As part of a project management plan, which states the work done to deliver a product, service, or results?

Project scope

Deliverable

Project charter

Portfolio

Project Scope

500

Which statement best describes the role of a project sponsor?

A non-key stakeholder.

The only stakeholder.

Not a stakeholder.

A key stakeholder.

A key stakeholder

500

During a project planning session for a playground project, a group of people also want the existing blacktop to be repaved, which is not part of the original project plan. Adding this will result in a budget increase. What else will be affected as part of the project plan? (Choose two)

Schedule

Scope

Number of resources

Quality

Schedule 

Scope

500

Match east project scenario with the approach used. 

Software app with well-defined requirements. 

A wheelchair with a strict base model but room to have multiple iterations. 

A logo design project with many versions and colors. 

Predictive - Software app with well-defined requirements. 

Adaptive - A logo design project with many versions and colors. 

Hybrid - A wheelchair with a strict base model but room to have multiple iterations.