During execution in a project to build a major road bridge, your team found a hefty flaw in the technical drawings. On an ad-hoc base, they had to find and implement a workaround to avoid delays and mitigate technical problems. What should you do next?
o Meticulously document the problem and the workaround to create a requested change to the project management plan, which will then be passed to the body responsible for the change control decision.
o The workaround was performed on a technical level only. As long as it does not influence the function of the bridge or the organizational configuration of the project, a change request will not be necessary.
o A formal change request from hind side is not sensible. Create some additional documents describing the workaround and sign them by yourself, you can present them during the next regular CCB meeting.
o It is normal in projects that, during project execution, inconsistencies arise between planning documents and actual implementation. This is no problem as long as the functional status of the product is maintained.
o Meticulously document the problem and the workaround to create a requested change to the project management plan, which will then be passed to the body responsible for the change control decision.