Governance Basics
Determining Governance
Escalation Paths
Thresholds & Controls
Governance Mindset & Exam Traps
100

This term refers to the framework, functions, and processes that guide project decision-making, oversight, and accountability.

What is project governance?

100

This type of project typically requires more formal governance, documentation, and oversight.

What are high-risk or high-complexity projects?

100

This is the documented route a project manager follows when an issue cannot be resolved at their level.

What is an escalation path?

100

This term refers to the triggers that require the PM to escalate issues, such as cost variance limits or schedule delays.

What are escalation thresholds?

100

Skipping governance planning often leads to unclear authority and this common project issue.

What is delayed decision-making?

200

This group provides high-level direction, approves major decisions, and ensures alignment with organizational strategy.

What is the governance board (or steering committee)?

200

When determining governance, the PM considers how decisions are made, who approves what, and how this is documented in this artifact.

What is the project management plan?

200

This component defines the specific conditions under which a problem must be elevated to a higher authority.

What are escalation thresholds?

200

A deviation of greater than 10% schedule variance might be an example of this governance element.

What is a predefined threshold?

200

This trap occurs when the PM escalates all issues, regardless of thresholds.

What is over-escalation?

300

This governance function ensures the project is monitored objectively for performance, compliance, and alignment with strategy.

What is oversight?

300

In adaptive environments, governance may rely more on this recurring event where work is reviewed and decisions are made.

What are ceremonies such as sprint reviews?

300

This person is typically the first point of escalation when issues exceed the PM's authority.

Who is the project sponsor?

300

These measurable limits help ensure the project stays aligned with cost, time, and scope expectations.

What are control thresholds?

300

This problem occurs when the PM assumes governance will “figure itself out” once the project begins.

What is lack of defined governance?

400

PMI recommends that project governance should reflect this larger existing structure whenever possible.

What is the organizational governance structure?

400

PMI recommends aligning project governance with this factor to ensure consistency and avoid confusion with enterprise standards.

What is existing organizational governance?

400

This governance element ensures that problems reach the correct person quickly based on urgency and impact.

What is the escalation hierarchy?

400

When thresholds are exceeded, this formal document may be required to adjust the baseline.

What is a change request?

400

PMI warns against setting escalation thresholds that are too low because it can overwhelm this group.

Who is the governance board or sponsor?

500

This component contains the rules, roles, and responsibilities that determine how the project is monitored and controlled.

What are governance guidelines?

500

This governance practice evaluates project performance at key points to decide whether to continue, change, or terminate the project.

What is a stage gate review?

500

These two factors—level of impact and level of authority—normally determine whether an issue should be escalated.

What are impact and decision authority?

500

Thresholds are designed to protect this element of project management, ensuring that deviations are managed properly.

What is the baseline?

500

This trap occurs when a PM designs governance that contradicts the organization’s existing structure, causing confusion.

What is misaligned governance?