Standard Processes
General
TPS & FPS
Takt Steering & Control
Team/Company Facts
100

Name of board that collects all boards in just one and has processes of internal items (Operations, HR, Marketing,etc.)

Company Systems & Miro Boards

100

What does S.M.A.R.T goals stand for?

Specific, Measurable, Achievable, Relevant, Timebound

100

What does IPCS ™ stand for?

Integrated Production Control System

100
What are the main physical resources we use to reinforce TS&C?
The Takt Boards
100

True or False: It's ok to multitask during Company Meeting, TRM and Leadership Meeting.

False.

200

What are the books that we (ideally) need to read on our first 3 months in the company?

-TPS, FPS, TSC, 2 Second Lean & Netflix Book

200

How many Tec Days are we required to attend annually?

10

200

What are the 6S?

Sort

Set in order

Shine

Standarize

Sustain/Self Discipline

Safety

200

What is the difference between Steering & Control?

Steering: Moving/Directing the train of trades and the system design (First planners-PM team).

Control: Controlling the environment in the field and reducing impacts (Last Planners-Field Team).

200

Name all persons of your pod.

Review board.

300

What are the items that need to be included in the project status dashboard?

-Project Informatíon (Title, days remaining, finish date, buffer remaining)

-Project progress by days

-Project Progress by activites

-BBP

-Phase progress (optional)

300

What should be always at the left of our project boards?

The Project Information (Get the Numbers Section), with information of the team and links to resources.

300

Identify, ... & ...

Identify, Discuss & Solve

300

What is Kaizen?

Continuous Improvement

300

How many women we have in the company?

26

400

Name 10 Standard Processes

Review Board:

-Kick-Off

-WDA

-Roadblocks

-Procurement

-Logistics

-Macro

-Pull Plan

-Email

-Lookaheads

-Fresh Eyes


400

What is the difference between substantial completion and final completion?

Substantial completion denotes that the project is sufficiently complete for its intended use, allowing the owner to assume possession and begin occupying the premises. Final completion indicates that all work has been fully finished, including the resolution of any outstanding issues or deficiencies.

400

What are the 6 most important meetings from the meeting system?

-Strategic planning

-TPM

-Morning huddle

-Crew Preparation huddle

-Foremen Huddle

-Daily team Huddle

400

What are the 4 main type of constraints?

Resources

Labor

Cost 

Space

400

How many people are we in the company?

54

500

WDA, Macro Shaping, Zone Maps, Logistics Maps, Project Strategy are all part of...

Gate 3
500

Name the  typical phases we would have for a standard project.

-Design

-Buyout/Procurement

-Site Pre/Make-ready

-Mobilization & Demolition (If needed)

-Foundations

-Superstructure

-Exteriors

-interiors

-Site Work

-Testing & Cx

500

Name the first 5 columns in the takt calculator.

-Takt Wagons

-Takt Zones

-Takt Time

-Duration

-Trade Time Gained

500

Name the 3 types of walks.

First Zone Walk

Handoff Walk

Standard Walk

500

Mention 3 of the company's quarterly goals.

-ELEVATE MACRO - LEVEL STRATEGIC PLANNING

-IMPLEMENT DASHBOARDS THAT SHOW US THE STATUS OF THE IPCS™

-IMPLEMENT POWER BI FOR EMAILS AND DASHBOARDS TO STREAMLINE THEIR CREATION

-INVOLVE THE CLIENT WITH STRATEGY -- GET FEEDBACK & IMPROVE OPERATIONS AND OUR ABILITY TO SHOW IT

-IMPLEMENT AI SO WE CAN FOCUS ON STRATEGY.