Formulas
Predictive Planning
Predictive Initiating & ITTOs
Predictive Planning 2
More ITTOs
100

The formula used to find the number of communication channels in a project

What is n(n-1)/2?

Ex. 10 Stakeholders = n

10(10-1)/2 = 45

100

Is the most accurate type of estimating technique

What is Bottom-up Estimating?

Breakdown the activities in more detail until you can assign resources, then aggregate into the full activity

100

The formal process to propose a change to a document or deliverable.

What is a Change Request?

100

Document used to effectively engage stakeholders

What is the Communications Management Plan?

100

Tool to compress a schedule involving adding additional resources to complete tasks.

What is Crashing a schedule? Always costly

Alternative is Fast Tracking, or performing activities in parallel. More risk to project.

200

25%-75% is this type of cost estimate

What is Rough Order of Magnitude Estimates?

200

Document that outlines acceptable behavior to follow within a project

What is a Team Charter?

Should include rules of conduct, decision-making methods, meeting cadence. 

200
Information needed to to determine whether a project should be invested in or not.
What is a Business Case?
200

Estimating method that relies on historical information to assign activity durations

What is Analogous Estimating? 

200

Output of Estimate Costs. Provides detail of how estimates were made and by whom.

What is Basis of Estimates?

300

3-Point formula of estimating activities that require an optimistic, pessimistic, and realistic duration estimates. 

What is the PERT formula? 

(O + (4R) + P)/6

300

The smallest breakdown of work to be completed from the project deliverables.

What are activities?

300

Technique of hiring SME or experts to help you plan or conduct a process.

What is expert judgement?

300

Smallest breakdown of work during the Plan Scope Management phase.

What are Work Breakdown Structures?

300

Sending out mass email blasts to all stakeholders is this type of communication tool

What is a push method?

Opposite is pull (ex. Instructing stakeholders to download files each week)

400

A number that indicates the amount of time a task can be delayed without impacting subsequent tasks

What is Free Float (or Slack)?

400

The output of Defining Scope

What is the project scope statement?

Output of the WBS is the Scope Baseline

400

Automated system tool that helps project managers optimize schedules

What is PMIS (PM Information Systems)?

400

All costs of a product over its lifetime to ensure it meets quality. Includes failure costs, prevention costs, conformance/non-conformance costs

What is the Cost of Quality?

400

Visual, non-linear way to organize data.

What is mind-mapping?

500

The optimistic estimate where the PERT estimate is 4, the realistic estimate is 4, and the pessimistic estimate is 6.

What is an optimistic estimate of 2 

PERT = (O + 4(R) + P)/6

4 = (O + 4(4) + 6)/6

4 = (O + 22)/6

24 = O + 22

2 = O

500

The money set aside in a project for identified, known risks and are part of the cost baseline.

What are contingencies reserves. 

Management reserves are not part of the cost baseline and are for unknown risks.

500

Output of Plan Scope Management that provides information on how requirements will be analyzed, documented, and managed

What is the Requirements Management Plan?

500

Activity sequencing relationship where completion of the successor work package depends on the start of its predecessor 

What is a Start to Finish Relationship?

500

Quality Metrics, or specifications on how quality will be measured is this type of ITTO to Plan Quality Management.

What is an Output?