Navigation
Activities
Logic/Relationships
Building a Schedule
Maintaining a Project
100
A column of buttons that allow for quick access to projects, activities, WBS, resources, etc.
What is the Directory Bar?
100
A tool that assists a user in creating a new Activity and must be enabled in the User Preferences.
What is the Activity Wizard?
100
It provides a view of relationships between Activities and displays the logical flow of a project.
What is the Activity Network?
100
Allows for the arrangement of data by a common attribute and determines the order in which items are displayed within each group.
What is Group and Sort?
100
The measure of the amount of work completed on an activity.
What is the Activity Percent Complete?
200
An area used to create, view and edit Activities for an open project.
What is the Activities Window?
200
Task Dependent: used to control the duration of the activity when no resources are assigned or when one or more resources are assigned to the same activity.
What is the default Activity Type for OPG?
200
The offset or delay between an activity and its Successor and is set for selected activities to meet special conditions in a schedule.
What is a Lag?
200
A tool for graphical display of information for groups of resources used for high level reporting.
What is the Stacked Resource Histogram?
200
The actual progress that is tracked and compared against a project's plan.
What is a Baseline?
300
An area used to adjust user specific settings and preferences including time and date display options.
What is the User Preferences?
300
The Duration Type - General Tab.
What is the field that defines how the completion time for the selected Activity is calculated?
300
The "dynamic zoom" function that changes your mouse cursor from a pointer to maginifying glass.
What is Alt + Click?
300
The Resources tab.
What is the area on an Activity you Assign Resources?
300
A tool used to define the statusing period for activities that need to be updated.
What is the Progress Spotlight?
400
Exclusive, Shared and Read Only.
What are the three Access Modes for opening an existing project?
400
Click on an Activity, select the Codes Tab, click the Assign button, select Activity Code Type, use Search Function for assistance searching and click OK button.
What is process for adding Activity Codes to an Activity?
400
The functionality that enables you step forward or backward through a sequence of activities to focus on Predecessor and Successor relationships.
What is Trace Logic?
400
Can be used to determine how many hours each resource is scheduled to work.
What is Resource Usage Profile?
400
Cars that can be displayed in the bar chart as Project, Primary, Secondary and Tertiary.
What are Baseline Bars?
500
A tool that displays information about available data items.
What is Hint Help?
500
A special type of User Defined Field (UDF) that enables you to select colour-coded icons as values for display in columns; group and sort; filters and reports (i.e. HOT ITEM).
What is the User Defined Field (UDF) type Indicator?
500
An indication of a Critical Path Activity.
What is a Red Border around an Activity box in Trace Logic?
500
Three different ways to screen data that will be displayed.
What is Default, Global and User Defined filters?
500
Location to enter Actual Start, Percent Complete and/or Remaining Duration data.
What is the Status Tab?