Vocabulary
Test
Schedule compression
100

What is Schedule compression

compressing a project schedule to make the project duration shorter.

100

The Work Breakdown Structure can BEST be thought of as an effective aid for __________ communications.

Stakeholder

100

What is one reason you would compress a project schedule.

A client wants you to complete the project early.

200

What is the work breakdown structure


The work to be executed by the project team to accomplish project objectives and create the required deliverables.

200

What is the lowest level of WBS components known as?

Work Package.

200

What is one way to crash a project time schedule

Add more employees to a project.

300

What is Project management software

Software Used to help plan, organize, and manage resource pools and develop resource elements

300

During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project. Which of the following documents contains the detailed description of work packages?

WBS dictionary

300

How is Crashing different from fast tracking.

Crashing adds more people to the project to make it go faster.

400

What is Bottom up Estimating

Method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS

400

Completion of a product scope is measured against

WBS and WBS dictionary

400

What are the Two types of Schedule compression

Fast Tracking and Crashing

500

What is verify scope 

the process of comparing the actual deliverables against what was documented within the scope baseline

500

Decomposition is an important tool used to

Create your WBS

500

What is the benefit to fast tracking

You can work on two things at once.