3.03
3.04
4.01
4.02
4.03
100

The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, a component of the project management plan. Components of the scope baseline include Project Scope Statement, WBS and WBS Dictionary.


What is scope statement?

100

The  process of comparing the actual deliverables against what was documented within the scope baseline.

What is verify scope?

100

The logical relationship where initiation of work of the successor activity depends upon the completion of work of the predecessor activity.

What is Finish-to-start?

100

The technique of estimating the costs or duration of projects and parts of a project.

What is Bottom-Up Estimating?

100

A technique where you identify tasks that are necessary for project completion and determine
scheduling flexibilities.

What is Critical Path method?

200

Document generated by the Create WBS process that supports the WBS. The WBS Dictionary provides more detailed descriptions of the components in the WBS.

What is WBS Dictionary?

200

the process of monitoring the status of the project and product scope and managing changes to the scope baseline

What is control scope?

200

The logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity.

What is Finish-to-finish?

200

Used to help plan, organize, and manage resource pools and develop resource elements

What is project management software?
200

Perform Schedule Network Analysis that considers
task dependencies, limited resource availability, and buffers.

What is Critical Chain Method?

300

The work to be executed by the project team to accomplish project objectives and create the required deliverables.

What is WBS

300

Project performance measurements are used to assess the magnitude of variation from the original scope baseline.

What is variance analysis.

300

The logical relationship where initiation of the work of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity.

What is Start-to-start?

300

Technique uses information from similar projects to establish a cost estimate based on the data
available.

What is Analogous estimating.

300

A technique in which start and finish dates are adjusted based on resource limitation with the
goal of balancing demand for resources with the available supply.

What is resource leveling?

400

Is the subdivision of project deliverables into small, more manageable components until the work and deliverables are defined to the work package level. The work package level is the lowest level in the WBS, and is the point at which the cost and activity durations for the work can be reliably estimated and managed. The level of detail for work packages will vary with the size and complexity of the project.

What is decomposition?

400

Deliverables that meet the acceptance criteria are formally signed off and approved by the customer or sponsor. Formal documentation received from the customer or sponsor acknowledging formal stakeholder acceptance of the project’s deliverables.

What is Accepted Deliverables?

400

The logical relationship where completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity.

What is Start-to-finish?

400

A statistical and accuracy-based technique for calculating the time,
cost, and resources needed for project success.

What is parametric estimating?

400

A business planning and modeling technique used to yield various projections for some outcome
based on selectively changing inputs.

What is What-if Scenario Analysis?

500

Decomposition is an important tool used to


What is Creating a WBS?

500

KEY output of Verify Scope process

What is Customer acceptance of project deliverables?

500

Project schedule network diagram is an important output to what.

What is sequence activities?

500

Activity Resource Requirements is an input to what

What is Estimate Activity Durations?


500

Process of shortening a project.

What is project crashing?