WBS
SEQUENCE
SOFTWARE
CRITICAL PATH
CRASHING
100

WBS are..

a. Task-oriented

b. Process-oriented

c. Deliverable-oriented

d. Time-oriented

c. Deliverable-oriented

100

Project schedule network diagram is an important output of which of the following processes?



Sequence activities


100

Activity Resource Requirements is an input to which of the following processes:


Estimate Activity Durations


100

what's the first step to determining critical path?

Write down the start and end time next to each activity.

100

what is one reason you´d need to crash a project?

open answer.

200

The ______ is utilized as the starting point for creating a WBS

a. Preliminary Project Scope Statement

b. Product Scope Description

c. Project Charter

c. Project Charter

200

Supper starts when the cooking is complete is an example of..

Finish-to-Start


200

Parametric Estimating is done as a part of which process


Estimate Activity Durations


200

can you determine the late start of activity A before finding the early start of the other activites?

no

200

how do you determine which activities should be crashed?

activities on the critical path.

300

The Work Breakdown Structure can BEST be thought of as an effective aid for __________ communications.



Stakeholder

300

the construction of walls before you move forward is what kind of dependency? 

Mandatory dependency


300

Reserve Analysis involves:


incorporating time buffers into the activity duration estimates


300
how do you know which activites need to be done to complete another activity?

predecessors 

300

how would you find the critical path?

Write down the start and end time next to each activity.

400

Completion of a product scope is measured against:


WBS & WBS Dictionary


400

when creating a sequence of events it´s important to be...

a. clever

b. literal

c. specific (go into detail)

c. specific (go into detail)

400

Your task is to set up a set of high-end servers in a data center.  You are very familiar with the process since you have set up 6 other similar data centers for the organization.   Which techique will you use for determining the project time line?


Three-point analysiis

400

what activity needs to be finish to start activity D?

A

400

which of these is a reason not to crash a project?

a. your schedule is behind 

b. you have extra time 

c. client needs it done sooner

b. you have extra time 

500

What is the lowest level of WBS components known as?


Work Package

500

A comprehensive list including all schedule activities required on the project is..

activity list

500

Your team is reviewing the project activities and has started to estimate the duration of the work packages identified in the WBS. Some of these work packages and activities have significant uncertainty associated with them for which the team has created contingency buffers. The tool and technique that is used for this process is called:



Reserve analysis


500

What activities determine if acivity F can start? 

C,D

500

what is the goal of crashing a project?

getting/keeping your project on schedule.