WBS are..
a. Task-oriented
b. Process-oriented
c. Deliverable-oriented
d. Time-oriented
c. Deliverable-oriented
Project schedule network diagram is an important output of which of the following processes?
Sequence activities
Activity Resource Requirements is an input to which of the following processes:
Estimate Activity Durations
what's the first step to determining critical path?
Write down the start and end time next to each activity.
what is one reason you´d need to crash a project?
open answer.
The ______ is utilized as the starting point for creating a WBS
a. Preliminary Project Scope Statement
b. Product Scope Description
c. Project Charter
c. Project Charter
Supper starts when the cooking is complete is an example of..
Finish-to-Start
Parametric Estimating is done as a part of which process
Estimate Activity Durations
can you determine the late start of activity A before finding the early start of the other activites?
no
how do you determine which activities should be crashed?
activities on the critical path.
The Work Breakdown Structure can BEST be thought of as an effective aid for __________ communications.
Stakeholder
the construction of walls before you move forward is what kind of dependency?
Mandatory dependency
Reserve Analysis involves:
incorporating time buffers into the activity duration estimates
predecessors
how would you find the critical path?
Write down the start and end time next to each activity.
Completion of a product scope is measured against:
WBS & WBS Dictionary
when creating a sequence of events it´s important to be...
a. clever
b. literal
c. specific (go into detail)
c. specific (go into detail)
Your task is to set up a set of high-end servers in a data center. You are very familiar with the process since you have set up 6 other similar data centers for the organization. Which techique will you use for determining the project time line?
Three-point analysiis
what activity needs to be finish to start activity D?
A
which of these is a reason not to crash a project?
a. your schedule is behind
b. you have extra time
c. client needs it done sooner
b. you have extra time
What is the lowest level of WBS components known as?
Work Package
A comprehensive list including all schedule activities required on the project is..
activity list
Your team is reviewing the project activities and has started to estimate the duration of the work packages identified in the WBS. Some of these work packages and activities have significant uncertainty associated with them for which the team has created contingency buffers. The tool and technique that is used for this process is called:
Reserve analysis
What activities determine if acivity F can start?
C,D
what is the goal of crashing a project?
getting/keeping your project on schedule.