What  does WBS stand for

Work Breakdown Structure

100

What is the word that describes all the main features of a project and what needs to happen?

scope

100

Specific points on a projects timeline

Project milestones

100

Best case: 6 days

Worst case: 13 days

Most likely: 8 days

Estimated time?


9 days
100

What does CPM stand for?

Critical path method

200

What is the lowest level of a WBS?

Work package

200

What is a tool used for controlling scope?

variance analysis

200

Project outlines that reduce rework and serve as a starting point

templates

200

What is the analysis of existing resources?

Reserve analysis

200

Critical path?

The tasks necessary for project completion

300

What does a WBS dictionary contain?

Detailed description of work packages

300

Who is most important in validating scope?

Project sponsor or customers

300

What type of chart is a Gantt chart

Bar chart

300

Things we use to help plan and organize our projects

Project management software

300

Performing tasks in parallel to get them done faster

Schedule fast tracking

400

What process do we use to create a WBS?

decomposition

400

What is the purpose of inspection

To make sure deliverables meet criteria

400

A task cannot be finished until its predecessor is finished

Finish-to-finish

400

What is reserve analysis a technique for?

estimate activity durations

400

Bringing in more resources to speed up a project

Project crashing

500

Components of what are listed in the project scope statement, WBS, and WBS dictionary

scope baseline

500

Accepted deliverables require formal documentation from who?

Stakeholders

500

Precedence diagramming method is a visual of what?

sequence activities

500

Technique for calculating time, cost, and resources needed for the project

Parametric estimating

500

What is the visual that contains everything that needs to be done in a project?

Precedence diagramming method