Project Manager
General Project Management
Project Management at TransLink
Project Scope
Project Schedule
100

The individual or individuals that the project manager must clearly define the project objective with.

Who is the customer (or sponsor)?

100

This document is used to authorize the project.

What is the project charter?

100

What is the name of TransLink's BTS bespoke project management framework?

Atlas.

100

A hierarchical decomposition of the project work scope into work packages that produce the project deliverables?

What is a work breakdown structure (WBS)?

100

The longest path in the overall network diagram.

What is the critical path?

200

Empowering a project team to achieve the project objective and allowing team members to successfully carry out assigned tasks.

What is delegation?

200

This form of communication is the best way to build relationships.

What is face-to-face meetings (or face-to-face)?

200

What is the bespoke framework, recently rolled out, that supports the delivery of solutions in a product increment fashion?

Release-based framework

200

The portion of the Project Scope Document that clearly defines the major tasks or work elements that will need to be performed by a project team or contractor?

What is the Statement of Work (SOW)?

200

Recorded time of when an activity is completed by the owner.

What is actual finish (AF)?

300

Computer software used to compare actual progress to planned progress.

What is a project management information system (PMIS)?

300

This document establishes good customer communications between customer and contractor by arriving at a mutual understanding and clear expectations.

What is a contract?

300

The project team needs to secure this stage approval prior to submit the SPA package over to CMC.

Stage 6 - Baseline Plan

300

This document shows appropriate sequence and dependency relationships of activities that need to be performed to accomplish the overall project work scope.

What is the network diagram?

300

A technique used to shorten the schedule duration for the least incremental cost by adding resources.

What is crashing?

400

This analytical skill helps project managers make data-driven decisions.

Critical thinking.

400

The quantitative conditions expected to be accomplished.

What is acceptance criteria?

400

What did the most recent Atlas framework update entail?

STRA completion timeline change

400

This type of plan assures work is done according to specifications and applicable standards and that deliverables meet acceptance criteria.

What is the quality plan?

400

A significant point or event in a project life cycle.

What is milestone?

500

This term refers to the ability of a project manager to influence and guide the project team towards achieving project goals.


Leadership.

500

This type of agreement states that the customer will pay the contractor a set amount regardless of actual cost.

What is fixed-price contract (or fixed-price)?

500

What is the full name of the board that governs changes to PROD environment at TransLink BTS?

CAB - Change Advisory Board.

500

These are the specifications of the deliverables used to tell you whether these were produced successfully.

Requirement.

500

Maximum amount of time a task may be delayed beyond its early start without delaying project completion.

What is Total slack?