A
B
C
D
E
100

This schedule involves resource utilization charts based on each activity's latest start time

What is as-late-as-possible (ALAP) schedule?

100

The time at which a specific activity is actually completed

What is actual finish time (AF)?

100

This chart is used for the representation of a project in which the activities are represented by horizontal segments, of which the length is proportional to the time necessary to conclude the task in question.

What is a bar chart?

100

The longest sequence of activities from project start to finish that must be completed to ensure the project is finished by a certain time

What is the critical path?

100

How much time a task can be delayed before a subsequent task — or the entire project itself — is likewise delayed

What is free slack?

200

A schedule is based on the earliest start time of each activity in the project.

What is an as-soon-as-possible (ASAP) schedule?

200

A technique in which start and finish dates are adjusted based on resource limitation with the goal of balancing demand for resources with the available supply

What is resource leveling?

200

The limitations of inputs available to complete a particular job: primarily people time, equipment and supplies

What is resource constrained planning?

200

How project managers find out how much capacity their team has over a period of time, and ascertain which of their resources are under or over-utilized

What is resource utilization?

200

The amount of time a task can be delayed before the project finish date is delayed

What is total slack?

300

A conceptual model used in project management that describes the stages involved in an information system development project, from an initial feasibility study through maintenance of the completed application

What is a systems development life cycle (SDLC)?

300

A project schedule whose schedule activities start dates, and finish dates directly reflect the availability of all resources in question

What is resource-limiting scheduling?

300

A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined limits

What is resource smoothing (or resource leveling)?

300

This describes the participation by various organizations, people and roles in completing tasks or deliverables for a project

What is a responsibility assignment matrix (RAM)?

300

A process of allocating tasks to human and non-human resources so that they're maximized for efficiency

What is a resource requirements plan? 

400

The listing of activities, deliverables, and milestones within a project, usually including the planned start and finish date, duration, and resources assigned to each activity.

What is a schedule?

400

This can be calculated using forward calculations in the project network and is equal to the maximum of the earliest finishing times of all its predecessor activities

What is earliest start time (ES)?

400

The limitations of inputs available to complete a particular job: primarily people time, equipment and supplies

What are resource constraints?

400

The most common type of constraints in project management, these deal with the processes required to complete an activity or assembly

What are technical constraints?

400

The activity's earliest start time plus the activity's estimated duration

What is earliest finish time?