Project Risk
Communication
Integration
Cost
Stakeholders
100

The process of identifying individual risks and documenting them.

What is Identify Risks?

100

This is the amount of time spent by a project manager communicating project information

What is 90%?

100

3 of the 10 things a Project Manager/Coordinator/ROW Agent should know.

What is Risk, Procurement, Cost, Resource, Stakeholder, Communication, Scope, Schedule, Quality, and Integration Management?

100

This is the ability to calculate the project’s estimated cost, request funding, and make sure dollars are adequately spent

What is Cost management?

100

This is the skill of knowing the frequency and best communication method to keep internal/external interest groups engaged

What is Stakeholder Management?

200

These are three techniques that can be used to identify project risks.

What is Interviewing, Brainstorming, Checklists, historical data, lessons learned register, seasonal trends?

200

The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.

What is Lessons Learned?

200

5 things a Project Manager/Coordinator/ROW Agent should Do.

What is Initiate, Plan, Execute, Monitor and Control, and close out a project?

200

This information is needed before a project manager can adequately estimate project costs

What is project requirements (customer requirements, project requirements, user requirements, etc.)?

200

These are two types of stakeholders

What is Internal and External?

300

These are the steps in risk planning.

What is Identify Risks, Analyze Risks, Plan Responses, Assign Owner, and Monitor and Contro?

300

Project documents, such as change log, lesson learned register, risk register, issue log, QA/QC log, and stakeholder register are examples of these..

What is Communication tools?

300

The Triple Constraint Triangle includes this.

What is scope, schedule, cost and quality?

300

This involves developing an approximation of expenses needed to complete the project.

You can use the 3-point estimation formula to help you.

What is Cost Estimating?

300

A stakeholder who is part of the project team is this type of stakeholder.

What is Internal stakeholder?

400

SMART criteria for risks.

What is Specific, Measurable, Action Oriented, Relevant and Time Sensitive?

400

A plan that describes how, when, and by whom information about the project will be shared.  Also, know as the 5W's.

What is the Communication Plan?


400
Integration

What is the practice of overlap and interaction in various phases of the project?

400

This includes controlling change to the project budget.

What is Cost Control?

400

The key benefit of this step is that it allows you to increase support and minimize stakeholder resistance.

What is Manage Stakeholder Engagement?

500

Probability * Impact = X.

What is Severity of the Risk?

500

Making sure that the informational needs of the project and its stakeholders are met. 

ex. following up with a stakeholder to ensure they received the email update.

What is Monitor Communications?

500

10 things a Project Manager/Coordinator/ROW Agent should know.

What is Risk, Procurement, Cost, Resource, Stakeholder, Communication, Scope, Schedule, Quality, and Integration Management?

500

The schedule and/or the scope is usually affected when there is a change to this. 

hint: triple constraint

What is Cost?

500

This table is broken into four sections labeled, Keep Satisfied; Monitor Closely; Monitor; and Keep Informed.

What is Power Interest grid?