Displeasing Dispositions
Procedural Procession
Nonconformance Nomenclature
Categorical Catch-all
Dubious Details
100

When a part can be fully reworked to meet specified requirements, the disposition is called: ______

Repair

100

Which is the first step identified by this quality procedure?

Identification of nonconforming items

100

What does NC stand for?

Non-conformity

100

Is QP-830-201 an even or odd number of pages long?

Even!

100

Which teams/employees at NDI need to be able to identify and initiate a nonconformance?

All of them

200

When a part is not able to be reworked or repaired, and has not yet been sold to a customer, what is the most common disposition

Scrap

200

What two portions of the nonconformance process is the initiator responsible for?

Filling out the NCR record and making QA/Operations aware that it has been done

200

What does QA stand for?

Quality Assurance

200

When is a Material Review Board required?

When the initial meeting between QA and Operations fails to identify a path forward

200

Where in our office are nonconforming items stored?

Grey tote bin in front of Shannon's desk

300

When a part has been purchased by NDI from another company, but is found to be nonconforming, what is a common disposition

Return to vendor

300

Initial evaluation of the nonconforming items is determined by which two parties?

QA and Operations

300

What does MRB stand for?

Material Review Board

300

Name the two databases in which part nonconformances and process nonconformances are recorded respectively

Epicor, TLM

300

When a part nonconformance is discovered after the part has been shipped to a customer, which alternative NDI process must be followed

Customer Complaints Process
400

A part dispositioned as "Scrap" can also be kept for the following, instead of being thrown out

Research and development use

400

MRBs, in addition to choosing the disposition, can trigger a revisiting of what risk-evaluation tool?

FMEA

400

What does NCR stand for?

Non-conformity Record

400

If a accept-as-is disposition is chosen, which department (not at the MRB) needs to sign off on the decision 

Regulatory Affairs

400

What is the functional difference between an NCR and an NCMR?

Nothing!

500

When a nonconforming part is sent back to vendor, but the vendor cannot themselves repair, rework, what is the common disposition

Credit/Replacement

500

In what timeline must an NCMR be closed/resolved

In a 'timely manner'

500

What does NCMR stand for?

Non-conforming Material Report

500

What is the difference between a nonconformance and a deviation

Nonconformance is an item not fulfilling a requirement. Deviation is a temporary change to a drawing or procedure to allow production to continue while improvements are made

500

What is one type of failed sensor calibration would trigger a nonconformance?

Novel failure mode, a failure which would indicate a larger product line problem, frequent recurring failures of known type, high cost nonconformity