400
A new project wished to adopt agile methodologies in order to save time and money. Requirements were proposed and discussed via conference calls with all stakeholders to save on time and travel costs. Each participant kept their own notes of what was discussed and agreed to, thereby eliminating the need to produce and review a written requirements document. Designs were discussed by developers using phone calls, texting, emails, instant messaging, ad hoc meetings in front of white boards and over bagels in the cafeteria. Each developer then produced code based on their own recollection of what had been discussed and agreed to, eliminating the cost of documentation for the design, data model, mockups, interfaces, meeting minutes and defects/issues. In this extreme scenario, what is the likely result when the QC group begins their work?
Since there is no documented requirements to provide the baseline, the QC does not know how to write the test cases or what to look for during testing