resistant linings
Anchor Systems
Demolition
Apprentice Evaluation
More Evaluation
100

how do you prep surface before hex metal install?

Blast or Grind to present clean surface.

100

Holds the lining in place/attached to shell

Anchors

100

Primary concern of any Demolition

Safety

100

The working lining is also Known as?

The Hot face lining.

100

once installed castable must be _____ before the burn-in?

Cured

200

Hex metal and Hex Mesh help retain _____ linings

Resistance linings

200

The tip of the anchor is _____ far from hot face?

One inch?

200

Many Refractory vessels shut down for?

Inspection

200

name four basic shapes of refractory brick.

straight, key, arch, Wedge

200

Plastic Refractories require no _____ prior to installation

Water

300

What are wall seats used for?

Lining wall support?

300

C clips / scissor clips Typically used for? 

Roof & sidewalls

300

who often is responsible demolition?

Bricklayers/Apprentices

300

Correct dimensions of a 9 inch straight refractory brick 

9"x 4.5 x 3

300

Name three methods of bonding of plastics?

Heat, Air, Chemically.

400

A dull sound when striking the lining indicates? 

Voids 

400

Y anchors are typically used for?

Thick linings/dual linings

400

Are visible glowing red spots on the shell?

Hot spots

400

Used for the lining of heat containing vessels.

Refractory materials

400

The back up lining prevent _____ from escaping?

Heat

500

What creates voids? 

Improper installation?

500

 Are used for higher temperature applications

Ceramic Anchors

500

Any Demolition job should be undertaken in accordance with?

Job specifications, company Policies,& government regulations.

500

how much water should be added before mixing castables?

20%

500

When hex mesh is used each Hex is filled with?

Refractory